APS Running Statistics; FY25 to Present
  Scheduled User   Hours User Beam Available hours User beam Availability (%) Total Faults Mean Time to Recovery Faults Per Day of Delivered Beam Delivered Integrated Current    (A-hr) Hours of Top-up Scheduled Top-up Injector Availability MTBF
Run24-3 1569.0 1527.2 97.3% 49 0.9 0.77 184.5 1304   31.2
Run25-1 1887.0 1775.0 94.1% 60 1.9 0.81 152.7 1559   29.6
Run25-2 1544.0 1506.10 97.5% 30 1.3 0.48 249.1       50.2
Run25-3 1953.0 1863.47 95.4% 49 1.8 0.63 287.6       38.0
Run26-1 1535.0 1446.30 94.2% 60 1.5 1.00 279.9       24.1
Run26-2 1336.0 1239.2 92.8% 34 2.8 0.66 213.7       36.4
                       
TOTAL 9824.0 9357.3 95.2% 282 1.7 0.72 1367.5 2863 #DIV/0!   33.2
Through12/22/25 the end of Run 2025-3