Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Tuesday, 01/25/00
|
|
|
0800-0900
|
Replace UPS for Zone-A ACIS, check radiation monitor, requiring a search of Zone A/B
|
Vacca
Forrestal
|
No injection
|
0800-0930
|
installation of a new Rad monitor
|
Pasky
|
No injection
|
0800-0930
|
Install an illumination source at L5; measure and document water pipings at linac to RF test area penetrations
|
Pasky
Berg
|
No injection
|
0800-1030
|
Switch to RF3/RF4, perform RF3 shutdown validation for ACIS/MPS and Investigate RF1 beam current problem
|
Nassiri
Bromberek
|
No injection
|
0900-1100
|
2 hours Investigation of SR dipole and S3A:S3
|
Carwardine
McNamara
|
No injection
|
0930-1000
|
Validation of linac modulator
|
Pasky
Trento
|
No injection
|
1000-1100
|
Injector beam ready
|
Pasky
OPS
|
No injection
|
1000-1400
|
4 hours Continue to tune DI water temperature control loop, require SR supplies, RF system on.
|
Swetin
|
Concurrent
|
1100-1200
|
Shielding verification with 30 mA stored beam, shutter support needed
|
Mohan
AOD/BO
|
Stored beam and injection
|
1100-1200
|
BM14 X-ray bpm operation, bpm checkout
|
Singh
Erwin
|
Stored beam and injection
|
1200-1400
|
Emittance/instability study
|
Emery
Harkay
Yao
|
Stored beam and injection
|
1400-1500
|
Timing setup of S6 Cerenkov detector
|
Emery
Pietryla
|
Stored beam and injection
|
1500-1530
|
SR injection test with shutters open, requiring at least 6ID shutters open
|
Yao
|
Stored beam and injection
|
1530-1600
|
Ready for user beam
|
Yao
OPS
|
Stored beam and injection
|
|
|
|
|