Machine Studies

Schedule for Run1-2,2000

Jan. 25, 0800 -1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 01/25/00

 

 

0800-0900

Replace UPS for Zone-A ACIS, check radiation monitor, requiring a search of Zone A/B

Vacca

Forrestal

No injection

0800-0930

installation of a new Rad monitor

Pasky

No injection

0800-0930

Install an illumination source at L5; measure and document water pipings at linac to RF test area penetrations

Pasky

Berg

 

No injection

0800-1030

Switch to RF3/RF4, perform RF3 shutdown validation for ACIS/MPS and Investigate RF1 beam current problem

Nassiri

Bromberek

No injection

0900-1100

2 hours Investigation of SR dipole and S3A:S3

Carwardine

McNamara

No injection

0930-1000

Validation of linac modulator

Pasky

Trento

No injection

1000-1100

Injector beam ready

Pasky

OPS

No injection

1000-1400

4 hours Continue to tune DI water temperature control loop, require SR supplies, RF system on.

Swetin

Concurrent

1100-1200

Shielding verification with 30 mA stored beam, shutter support needed

Mohan

AOD/BO

Stored beam and injection

1100-1200

BM14 X-ray bpm operation, bpm checkout

Singh

Erwin

Stored beam and injection

1200-1400

Emittance/instability study

Emery

Harkay

Yao

Stored beam and injection

1400-1500

Timing setup of S6 Cerenkov detector

Emery

Pietryla

Stored beam and injection

1500-1530

SR injection test with shutters open, requiring at least 6ID shutters open

Yao

Stored beam and injection

1530-1600

Ready for user beam

Yao

OPS

Stored beam and injection