Machine Studies

Schedule for Run1-3,2000

Jan.31, 0800 - Feb.2, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 01/31/00

 

 

0800-1000

Inspect S24/25 raw supply for interlock error

Carwardine

PS

No beam

0800-1000

Run the wire for multipactor detection system on S40 cavities, including its rack, no access to zone-F

Song

 

No beam

0800-1000

Commission new air handling unit for SR dipole room

Carwardine

PS

No beam

0800-1000

Check and re-setup converters S27A:H3 and S28A:H3

Carwardine

PS

No beam

0800-1000

Change GRIZWOLD cartridges of absorbers in S4 and S36

Putnam

No beam

1100-1200

Verify the timing of SR injection septa

Hillman

Goetzen

No beam

0800-1200

BPM repair, need access zone-A-E

Erwin

Singh

No beam

0800-0900

Shutoff Rad monitor to see the readback change

Yao

No beam

0800-1200

Parallel Klystron operations study without beam requires Zone-F in test mode

Nassiri

Horan

No injection

1200-1400

Parallel Klystron operations study with beam

Nassiri

Horan

Stored beam and injection

0800-1600

RF1 gain problem investigation

Bromberek

Nassiri

Concurrent

1200-1400

Investigate the Unselected Dac problem

Carwardine

PS

Stored beam and injection

1400-1500

Re-measure orbit feedback response matrix following S27/28 corrector work

Carwardine

PS

Stored beam and injection

1500-1900

BM14 X-ray bpm feedback test

Singh

Emery

Lenkszus

Stored beam and injection

1900-2300

Characterize different beta-y lattices

 

Emery

Stored beam and injection

2300-2400

Take bpm data of feedforward corrector compensating the septum leakage field study

Emery

Stored beam and injection

2300-2400

Linac to booster injection

Sereno

No injection

 

Tuesday, 02/01/00

 

 

0000-0500

Thermal effect on orbit study

Emery

No injection

0000-0700

Continue Linac to booster injection

Sereno

No injection

0700-0900

Single bunch current limit study

Kathy

Eliane

Huang

Stored beam and injection

0900-1100

STUDY TIME AVAILABLE

 

Stored beam and injection

1100-1300

Continue single bunch current limit study

Kathy

Eliane

Huang

Stored beam and injection

1300-1700

shielding verification with 12mA and 30mA

Mohan

Stored beam and injection

1700-2300

High dispersion lattice setup

Chae

Stored beam and injection

2300-2400

BPM offset measurement at P3/P4

Emery

Stored beam and injection

 

 

Wednesday, 02/02/00

 

 

0000-0100

Continue BPM offset measurement at P3/P4

Emery

Stored beam and injection

0100-0300

Orbit corrected to zero setpoint

Emery

Stored beam and injection

0300-0700

Injection loss study with Cerekov detector, shutter support needed for at least 6ID, all gaps will be left open.

Emery

Stored beam and injection

0700-0800

Ready for user beam

Yao

OPS

Stored beam and injection