Machine Studies

Schedule for Run1-9,2000

March 13, 0800 - March 15, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 03/13/00

 

 

0800-2400

Top-up studies

Users

Boland

Yao

OPS

Stored beam and injection

 

Tuesday, 03/14/00

 

 

0000-0800

Continue top-up studies

Users

Borland

Yao

OPS

Stored beam and injection

 

0800-1000

Investigate possible PAR RF phase problem

Smith

PAR injection

0800-1000

Replace PEEL chips in S1B:P4 SCDU unit

Erwin

No beam

0800-1200

Authorized access Zone A to fix 8BM EPS problem

Stoffel

No beam

0800-1200

Authorized access Zone A to install test equipment on 1ID

Mohan

No beam

0800-1200

Authorized access Zone A to remove 5mm IDVC for re-certification

Gagliano

No beam

1000-1200

Access to zone-F to open/restart turbo bump on S36 cavities

Bromberek

No beam

1000-1200

Access zone-F to replace video fiber into S35 BM pinhole camera

Yang

Stevens

No beam

1000-1200

SR operations training

Yao

OPS

No beam

1200-1400

Shielding verification for 8BM and 4ID (10 mA for 45 min. and followed by 30 mA)

Mohan

Stored beam and injection

1400-1600

Continue shielding verification for 8BM and 4ID (10 mA for 45 min. and followed by 30 mA)

Mohan

Stored beam, no injection

1400-2200

Linac to booster injection

Sereno

No injection

1600-2000

OAG software test

Borland

No injection

1600-2000

Linac/LEUTL PEM test

Soliday

No injection

2000-2200

SR operations training

OPS

Stored beam and injection

2200-2400

32ID Xray BPM scans

Singh

Stored beam and injection

 

Wednesday, 03/15/00

 

 

0000-0200

Continue 32ID Xray BPM scans

Singh

Stored beam and injection

0200-0400

Bunch phase vs bunch current measurement

Yang

Stored beam and injection

0400-0700

Study Time Available

 

 

0700-0800

Ready for user beam

 

Stored beam and injection