Schedule for Run2-7,2000

June 19th, 0800 - June 21th, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 06/19/00

 

 

0800-1130

S19A:V2 tests

T. Fors

No beam

1130-1200

Get SR ready for injection

OPS

Stored beam and injection

0800-1000

RF klystron voltage change

D. Horan

No beam

0800-1000

Linac PS MEDM screen testing

McNamara

No beam

0800-1000

Install software for X-ray blade offsets

F. Lenkszus

No beam

0800-1100

SR dipole trim windings

J. Wang

No beam

0830-0930

Zone A access for ID3 and
2BM Xray blade connections

Erdmann
T. Roberts

No beam

0930-1030

Sector 2&3 bitbus errors

A. Hillman
ASD-CTL

No beam

1200-1800

Shielding verification for ID34.

Mohan

Stored beam and injection

1200-1800

Measure undulator gap effect on orbit
correction. Parasitic to shielding
verification.

Emery

Stored beam and injection

1800-2200

ID VC impedance measurement

Emery
Decker

Stored beam and injection

2200-2400

New filters on S25 bpms

B. Lill
L. Erwin

Stored beam and injection

 

Tuesday, 06/20/00

 

 

0000-0400

New filters on S25 bpms

B. Lill

Stored beam and injection

0400-0900

Chromaticity mapping

K. Harkay

Stored beam and injection

0900-1300

Single bunch instability

K. Harkay
Z. Huang

Stored beam and injection

1300-1700

EMW studies

C. Yao

Stored beam and injection

1700-1900

ID35 etax bump lattice work

L. Emery

Stored beam and injection

1900-2100

100 Hz bitbus sampling

T. Fors

Stored beam and injection

2100-2400

Microwave instability 2 f_s measurement

J. Song
Y. Chae
A. Lumpkin

Stored beam and injection

 

Wednesday, 06/21/00

 

 

0000-0400

Converging betax lattice correction and
optical measurements

L. Emery
V. Sajaev

Stored beam and injection

0400-0730

Orbit feedback development

C. Schwartz
Carwardine

Stored beam and injection

0730-0800

SR User run startup

OPS

Stored beam and injection