Machine Studies

Schedule for Run3-3,2000

July 15th, 0800 - August 15th, 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 08/15/00

 

 

0800-0900

Swap/fix S33A:S1 and S31A:S2 problem

Carwardine

PS

No beam

0800-0900

Diagnose S2/3 communication problem

Carwardine

PS

No beam

0800-0900

Waveguide switch to RF2, validation and test

Horan

Nassiri

No beam

0900-1300

4nm Emittance lattice study

Emery

Stored beam and injection

1300-1330

Waveguide switch back to RF1/3 (in parallel with SR magnet conditioning)

Horan

Nassiri

No beam

1330-1530

SR injection efficiency study

Emery

Stored beam and injection

1530-1600

Ready for User beam with singlet bunch fill pattern

OPS

Stored beam and injection