Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Tuesday, September 12
|
|
|
0800-0930
|
Access Zone F to test S39 flag, control access, full LOTO
|
Berg
|
No beam
|
0800-0900
|
Switch to RF4 for beam test (may need to switch back to RF1 for user run)
|
Horan
|
No beam
|
0930-1100
|
Test SR dipole DAC interface
|
McNamara
|
No beam
|
0800-0830
|
Swap our Altera chip in the bit-bus sniffer
|
Fors
|
No beam
|
0730-1100
|
Install flag camera for bunch compressor, need access Linac, AA and full LOTO
|
Yang
|
No Injection
|
0800-1100
|
Test 100 Hz and USDac SCAN fields
|
Fors
|
No beam
|
0800-1100
|
Replace and investigate S31B:V3 and S18B:Q1 supplies
|
Carwardine
|
No beam
|
0800-0900
|
Remove unused SR trim converters from SR.
|
Seglem
|
No beam
|
0900-1000
|
Investigate AGC loop disengage problem
|
Nassiri
Horan
|
No beam
|
1100-1500
|
Commissioning X-ray bpm feedback
|
Decker
Singh
Erwin
|
Stored beam and injection
|
1500-1530
|
SR lifetime study
|
Yao
|
Stored beam and injection
|
1530-1600
|
Ready for User beam with singlet bunch fill pattern
|
OPS
|