Machine Studies

Schedule for Run1-10,2001

March 20, 0800 - 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 03/20/01

 

 

0800-1000

Access zone-A for CPU installation preparation, control access, switch gear LOTO

Trakhtenberg

No beam

0800-1000

Access zone-D for BPM work, control access, switch gear LOTO

Erwin

Lill

No beam

0800-0900

investigate rebooting problem

Dimonte

No beam

0800-1000

Bring RF power from L3 into RF gun test area

Lewellen

No beam

0800-1000

Inspect filter capacitors of booster QF and QD

Puttkammer

No beam

0800-0900

access booster tunnel to inspect corrector magnets, authorized access, switch gear LOTO

Hillman

ASD-ME

No beam

0800-1000

Test new SR corrector database in one double sector (40&1), reboot vp ioc several time, may trip supplies.

Maclean

No beam

0800-1000

Fix readback glitches on S38/39

Fors

No beam

0900-1100

Operator re-qualification

Yao

Flood

Injection at 1000

1000-1200

Continue studies on RTFB/orbit correction overlap

Schwartz

Emery

Stored beam and injection

1200-1430

BPM test with new installed filter and comparator

Decker

Singh

Lill

Stored beam and injection

1430-1530

Dynamic aperture for high current single bunch beam

Harkay

Stored beam and injection

1530-1600

Ready for top up user beam

OPS

Stored beam and injection