Machine Studies

Schedule for Run1-2,2001

January 23, 0800 - 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 01/23/01

 

 

0730-1000

Run PAR septum to remedy BESOCM noise issue (control access, no group loto, no loto for PAR kickers)

Banks

Pietryla

Mcnamara

Gold

No beam

0800-1000

Repair 19ID shutter (Zone-C control access with switch gear loto)

Mohan

No beam

0800-0900

Check 14BM P2B cable connectors (Zone B control access with switch gear loto)

Hahne

No beam

0800-0830

Check waveguide/coupler interface alignment (control access with switch gear loto)

Nassiri

Bromberek

No beam

0800-1030

Switch to RF3, and test

Nassiri

Cours

No beam

0800-0900

Investigate S24/25 raw supply trips

Carwardine

PS

No beam

0800-0900

Reboot bpm iocs

Lenkszus

No beam

0800-1030

Operator training

Ops

No beam

1030-1230

Low emittance lattice studies

Emery

Stored beam and injection

 

1230-1330

S35 beta-function measurement

Emery

Stored beam and injection

 

1330-1430

Cerenkov detector timing

Emery

Stored beam and injection

 

1430-1530

Comission BM14/13 xbpm orbit feedback

Emery

Singh

Stored beam and injection

 

1530-1600

Ready for User beam

OPS

Stored beam and injection