Machine Studies

Schedule for Run1-9,2001

March 12, 0800 - March 14, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 03/12/01

 

 

0730-1030

Diagnose and fix readback missing bit for booster extraction septum

Hillman

Goetzen

No beam

0800-1000

Return RF waveguide to normal mode

Horan

Nassiri

RF Group

No beam

0800-1000

Shutdown electrical panel PP-R2 located in Bldg. 420 in order to remove wiring in conduit.

Janik

AOD-CF

No beam

0800-1000

Install Filter/Comp. in S25, Zone-D, control access, switch gear LOTO

Erwin

Lill

No beam

0800-1000

Troubleshoot S27 cabinet2 and S14 cabinet5 readback glitches without beam

Fors

No beam

0800-0900

Measure sextupole chamber clearance, zone-D access

Kim

No beam

1000-1200

Troubleshoot S27 cabinet2 and S14 cabinet5 readback glitches with beam

Fors

Stored beam and injection

1000-1200

Operator qualification

Yao

Schroeder

Stored beam and injection

1200-1500

Test Filter/Comp.

Decker

Lill

Stored beam and injection

1500-1800

DBPLD tests for ID14/32

Singh

Pietryla

Stored beam and injection

1800-2400

Low emittance lattice studies

Emery

Sajaev

Stored beam and injection

 

Tuesday, 03/13/01

 

 

0000-0400

Converging beta lattice

Sajaev

Stored beam and injection

0400-0800

High bunch current imaging study

Yang

Stored beam and injection

0800-1200

Feedforward study

Borland

Stored beam and injection

1200-1400

Operator qualification

Yao

Jones

Stored beam and injection

1200-1400

Operator qualification (booster)

Sawatski

Stored beam and injection

1400-2200

X-ray BPM test

Decker

Singh

Stored beam and injection

2200-2400

Quad corrected lattice for installation

Emery

Stored beam and injection

 

Wednesday, 03/14/01

 

 

0000-0200

Quad corrected lattice for installation

Emery

Stored beam and injection

0200-0630

Beam loss study with scrapers, cerenkov detector

Emery

Stored beam and injection

0630-0800

Ready for top up user beam

OPS

Stored beam and injection