Schedule for Run2-2,2000

May 15th, 0800 - May 15th, 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 5/15/01

 

 

0730-0930

Replace transistor on RFG-1 in linac.

Klick

No stored beam, no
injection

0800-0900

Switch RF, MPS validation, and other checks.

RF

No stored beam

0800-0900

Test a mapping database for DBPLDs

Lenkszus

No stored beam

0800-0900

New bitbus communication controller in IOCS1VP

Stein

No stored beam

0800-0900

S35ID and BM front end work. Trips MPS.

Mohan

No stored beam

0800-0900

Griswald flow meter work. Trips MPS

Putnam

No stored beam

0930-1000

Reboot test with beam

Dimonte

Stored beam and injection

1000-1230

SR lattice characterization

Emery

Stored beam and injection

1230-1430

Operator SR training

OPS

Stored beam and injection

1430-1530

Model independent analysis.

Borland
Wang
Sajaev

Stored beam and injection

1530-1600

User beam setup.

OPS

Stored beam and injection