Machine Studies

Schedule for Run3-2,2001

August 7, 0800 - 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 08/07/01

 

 

0800-0830

Waveguide switch to RF1/RF3 and perform ACIS/MPS validation

Forrestal

Arnold

OPS

 

No beam

0830-1000

Replace Griswold catridge in selected sector

Putnam

No beam

0830-1000

Remove and Replace fiber optic components used to link the P0 timing signal between the MCR and ICR. PAR Extraction will be inhibited briefly

Lenkszus

No beam

0800-1000

Install fiber interface boards on selected sector

Hillmana

No beam

1000-1200

RF2 phase loop trouble shooting. Reboot test of iocrf3hvps and iocrfsource.

Nassiri

Horan

Dimonte

Stored beam and injection

1200-1400

Xray BPM study

Singh

Decker

Stored beam and injection

1400-1530

DC/RT overlap study

Emery

Schwartz

Stored beam and injection

1530-1600

Ready for user beam

Yao

OPS

Stored beam and injection

 

End of Studies