Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Monday, 08/13/01
|
|
|
0800-1000
|
Tour of linac and leutl tunnel, linac in AA mode
|
Milton
|
No beam
|
0800-0900
|
RG2 Tune measurement
|
Nassiri
|
No beam
|
0800-0900
|
Install a microphone in the bunch compressor area
|
Pasky
|
No beam
|
0800-1000
|
Linac ioc network hardware replacement
|
Maclean
|
No beam
|
0800-0900
|
Install trigger and interlock cards
|
Grelick
|
No beam
|
0800-1000
|
Change clogging Griswold units in selected sectors, needs to turn off magnet supplies.
|
Putnam
|
No beam
|
0800-1200
|
Replace RF2 klystron
|
Horan
|
No beam
|
0800-1200
|
Replace RF rad. monitor at RF4
|
Jefferson
|
No beam
|
0800-1200
|
PS fiber board installation in selected sectors
|
Hillman
|
No beam
|
0800-1100
|
Disable control power temperature fault in converters
|
Fors
|
No beam
|
1100-1400
|
Investigate SR dipole current problem
|
J. Wang
Fors
|
No beam
|
1100-1200
|
PAR RF studies
|
T. Smith
|
PAR injection
|
1200-1600
|
Conditioning RF2 new klystron, possibly with beam.
|
Horan
|
Stored beam and injection
|
1400-1500
|
SR Operator training
|
OPS
Oakley
|
Stored beam and injection
|
1600-2400
|
Low emittance studies
|
Emery
|
Stored beam and injection
|
|
Tuesday, 08/14/01
|
|
|
0000-0700
|
Timing scan/orbit feedback
|
Singh
Decker
|
Stored beam and injection
|
0700-0800
|
Operator training
|
Oakley
OPS
|
Stored beam and injection
|
0800-1200
|
Single bunch instability
|
Harkay
Lessner
|
Store beam and injection
|
1200-1700
|
topup test in low emittance lattice with 2 nC from linac
|
Borland
|
Stored beam and injection
|
1200-1700
|
ADC 750 test
|
Emery
|
Store beam and injection
|
1200-1700
|
ID feedforward studies
|
Sereno
|
Store beam and injection
|
1700-2100
|
Injection efficiency studies with Cerekov detector
|
Emery
|
Stored beam and injection
|
2100-2400
|
ID chamber impedance
|
Emery
|
Stored beam and injection
|
|
Wednesday, 08/15/01
|
|
|
0000-0700
|
low current narrow band bpm study
|
Singh
Decker
|
Stored beam and injection
|
0700-0800
|
Ready for user beam
|
Yao
OPS
|
Stored beam and injection
|
|
End of Studies
|
|
|