Machine Studies

Schedule for Run3-4,2001

August 21, 0800 - 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 08/21/01

 

 

0800-0815

RF3 HVPS IOC reboot

Dimonte

No beam

0815-0915

Tying Johnson controls, control devices near 514

Andrew

Stevens

No beam

0815-0915

Re-install UPS on 6ID FE EPS/PSS

Friedman

No beam

0815-0900

Increase memory of iocsrscope

Gunerson

No beam

0815-1015

Change out more griswolds in the absorber circuits

Putnam

No beam

0815-1015

Backflush the water path for S27B:Q4

Carwardine

No beam

0815-1015

Repair water leak in S4A:V2

Carwardine

No beam

0815-0845

Waveguide switch to RF2/4

Horan

No beam

0815-1015

Investigate Dac problem with S32/33

Carwardine

 

No beam

0815-1200

Continue fiber receiver installation.

Hillman

No beam

0815-1200

Continue bypassing water OT interlock in Zone E

Fors

No beam

0815-1100

Verify wiring of booster bypass PSs

Hillman

No beam

1100-1200

Booster RF frequency change test

Sereno

No beam

0845-1200

RF conditioning without beam

Horan

Grelick

No beam

1200-1330

RF conditioning beam

Horan

Grelick

Stored beam and injection

1200-1330

Operator training

Sawatski

OPS

Stored beam and injection

1330-1530

Test various software with beam

Emery

Stored beam and injection

1530-1600

Ready for user beam

Yao

OPS

Stored beam and injection

 

End of Studies