Machine Studies

Schedule for Run4-3,2001

November 12, 0800 to November 14, 0800

Time

Descriptions

Studiers

SRStatus

 

Monday, 11/12/01

 

 

0800-0810

Acquiring SR kicker/Septum waveforms

OPS

Store beam and injection

0800-1000

Investigate L1 modulator arcing

Pasky

Meyer

No beam

0810-1010

Insert stainless steel coils into griswolds in the absorber circuits

Putnam

no beam

0800-1200

study and try to identify the noise on the AC

power line that has been causing problems for the gun heater and supplies in the rack

Markovich

No beam

0810-1000

Re-calibrate S38 cavity over power trips to account for cable modifications.

Grelick

no beam

0810-1200

study new capacitors for the booster

quadrupole power supplies

J. Wang

No beam

0810-1200

Bring on line or repair the dynamic mode of the Storage Ring

Correctors,

S15A:H1, S23B:V3, S32B:V1 and S9A:H3 they are not working in the dynamic mode

Hillman

no beam

1000-1200

Operator training (Linac)

OPS

Linac/Par beam

1100-1300

Inter-station phase calibration with 100mA stored beam

Horan

Nassiri

Store beam and injection

1300-1600

Response matrix measurement for low emittance lattice

Sajaev

Emery

Store beam and injection

1600-2000

Characterization of the corrected lattice

Sajaev

Emery

Store beam and injection

2000-2400

Sextupole scan to improve beam lifetime of low emittance lattice and SR injection study

Emery

Sajaev

Store beam and injection

 

Tuesday, 11/13/01

 

 

0000-0300

Setup PC gun for SR injection, and measure SR bunch purity

Lewellen

 

 

Linac beam

0300-1100

CSR studies in the linac with PC gun

Borland

 

 

Linac beam

1100-1300

Operator training (fill the ring first for Xbpm study)

OPS

 

 

Store beam and injection

1300-1800

AC mode tune of CPU

Vasserman

Emery

 

 

Store beam and injection

1100-1800

Test Xbpm/P0 gain script (parasitic with othe study)

Singh

Shang

Erwin

Hahne

Store beam and injection

1800-2000

Test Xbpm/P0 gain script

Singh

Shang

Erwin

Hahne

Store beam and injection

2000-2400

ID Xbpm work

Decker

Singh

Store beam and injection

 

Wednesday, 11/14/01

 

 

0000-0300

SR orbit work

Singh

Decker

Store beam and injection

0300-0700

Low emittance lattice/top-up study

Emery

Sajaev

Store beam and injection

0700-0800

Ready for user beam with low emittance and top-up

Yao

OPS

Stored beam and injection

 

End of Studies