Machine Studies

Schedule for Run1-3,2002

Feb 4th, 0800 - Feb 6th, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 2/4/02

 

 

0800

Stop injection and leave 100 mA stored

OPS

Stored beam and no injection

0800-1600

PAR access for RF cavity arc investigation

RF group

Stored beam and no injection

0800-1000

Linac access for linac alignment laser

Berg
Lumpkin

Stored beam and no injection

0800-1200

CPU AC mode correction. No injection possible.

Emery
Sereno
Vasserman

Stored beam and no injection

0800-1000

Test backup ADC750 digitizer

Lenkszus

Stored beam and no injection

0800-1000

Booster correctors B2CH3 & B2CH2.
Perform visual inspection of B:QD

PS group

Stored beam and no injection

1200

Dump SR beam

OPS

No beam

1200-1400

Test S14B:P4 Mpbpm

Lill
Erwin

No beam

1200-1300

Thermal imaging of SR dipole PS.

PS group

No beam

1200-1600

Check SR corrector signals in each converter.

PS group

No beam

1600-2000

Vary damping partition of low-emittance lattice

Borland

Stored beam and injection

2000-2400

Booster injection response and lower emittance booster

Sereno

Stored beam and injection

2000-2200

SR RF HOM

Song

Stored beam and injection

2200-2300

RTFB reboot test

Pietryla
Singh

Stored beam and injection

2200-2400

ID xbpm/ Mpbpm tests

Singh
Hahne
Erwin
Lill

Stored beam and injection

 

Tuesday, 2/5/02

 

 

0000-0400

Booster injection response and lower emittance booster (cont'd)

Sereno

Stored beam and injection

0000-0400

ID xbpm/ Mpbpm tests (cont'd)

Singh
Hahne
Erwin
Lill

Stored beam and injection

0400-0600

SR training

Rivera

Stored beam and injection

0600-0800

Disconnect 352MHz to MCR to make power and phase measurements

Laird
Lenkszus
Horan

No beam

0800

Inject to 100 mA

OPS

Stored beam and injection

0800-1000

Measure coupling perturbation of all IDs.

Emery

Stored beam and no injection

0800-1000

Booster/SR/LINAC training

Shultes
Hill

Stored beam and no injection

1000-1600

RG1 evaluation

Borland
Soliday

Stored beam and no injection

1000-1600

Linac signal observations

Grelick
Yoder

Stored beam and no injection

1600-1800

14-ID-A station shielding verification. 30 mA.

Mohan

Stored beam and injection

1800-2000

Lattice correction for low-emittance

Emery

Stored beam and injection

2000-2200

Dispersion correction for long. inj. lattice

Emery

Stored beam and injection

2200-2400

Minimization and verification of injection transient in longitudinal injection

Emery Chae

Stored beam and injection

 

Wednesday, 2/6/02

 

 

0000-0500

Orbit tests.

Decker
Singh

Stored beam and injection

0500-0700

Datapool orbit correction and pem tests.

Emery
Shang

Stored beam and injection

0700-0800

Standardize and prepare low-emittance top-up

OPS

Stored beam and injection