Schedule for Run1-4,2002

02/12, 0000 to 16000

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 02/12/02

 

 

0000-0300

Optimize the chromaticity for high single bunch current beam

Harkay

Stored beam and injection

0300-0500

Operator training for linac

Hill

OPS

Stored beam and injection

0500-0900

Investigating linac grounding problem

Pasky

no injection

0500-0900

Connect vac power supply to RG1 for conditioning

Goeppner

no injection

Storedbeam

0500-0900

PAR RF investigation

Smith

no injectionStoredbeam

0700-0900

Investigation of RG1 heater power

measurement

PS

 

no injection

Storedbeam

0900-1300

RG1 study

Borland

 

Stored beam and injection

0900-1100

CPU study

Emery

Stored beam, no injection

1100-1300

Orbit and data pool tests

Singh

Emery

Stored beam and injection

1300-1500

Longitudinal injection lattice correction

Emery

Stored beam and injection

1500-1600

Top-up beam for users

OPS

Yao

Stored beam and injection

 

End of Studies