Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Monday, 03/04/02
|
|
|
0800-0815
|
Collect xbpm user orbit reference with beam, stored beam, no top-up
|
Singh
|
Stored beam and injection
|
0815-0915
|
Investigate and eliminate the periodic crashes of ioclic2
|
Arnold
|
No beam
|
0815-1200
|
Inspect SR IK1, IK3, IK4 for loose wire
|
McNamara
|
No beam
|
0815-1200
|
Continue the repair of SR corrector reservoir capacitor crimp in zone B (no access)
|
McNamara
|
No beam
|
0815-1200
|
Continue to verify corrector feed-forward signals in zone-C and D (no access)
|
McNamara
|
No beam
|
0815-1000
|
Installation of an upgraded motorized phase shifter
|
Grelick
|
No beam
|
0815-0930
|
Visually inspect the RF4 ACIS interface for evidence of a defective AC power relay
|
Horan
|
No beam
|
1000-1100
|
Setup RG1 to support machine studies
|
Pasky
|
No beam
|
0815-0930
|
Replace the circulator TCU bias potentiometers at RF3 and RF5.
|
Horan
|
No beam
|
0800-1200
|
PSS rewiring, requires 5BM offline
|
Ross
|
No beam
|
0815-0930
|
P0 signal investigation
|
Nassiri
|
No beam
|
0815-1200
|
Access booster to upgrade booster filter/comparator
|
Lill
Singh
|
No beam
|
0800-1200
|
Par scope problem investigation
|
Borland
Stein
|
No beam
|
1200-1600
|
Local bump impedance measurements with fast orbit correction
|
Emery
|
Stored beam, and injection
|
1600-2000
|
Test of ID gap FF coefficient measurement with fast orbit correction
|
Emery
|
Stored beam, and injection
|
2000-2100
|
Booster/SR training
|
Shultes
|
Stored beam, and injection
|
2100-2400
|
High Emittance lattice orbit recovery
|
Singh
Decker
|
Stored beam and injection
|
2100-2400
|
Test booster longitudinal controllaw using PAR rf phase knobs, SR injection may be needed.
|
Sereno
|
Stored beam and injection
|
|
Tuesday, 03/05/02
|
|
|
2400-0300
|
High Emittance lattice orbit recovery
|
Singh
Decker
|
Stored beam and injection
|
0300-0500
|
Booster operator training, switch back to RG2
|
Sutton
|
Stored beam and injection
|
0500-0600
|
Switch the linac back to RG2
|
OPS
|
Stored beam and injection
|
0600-1000
|
Top-up with RG2 to booster injection
|
Borland
|
stored beam, no injection
|
0900-1100
|
Operator SR qualification
|
Rivera
Yao
|
Stored beam and injection
|
1100-1500
|
Orbit control test with RAW CA and some changes
|
Emery
Shang
|
Stored beam and injection
|
1500-1900
|
CPU AC mode measurement tests.
|
Emery
Sereno
Vasserman
|
Stored beam, and injection
|
1900-2200
|
Long. injection lattice correction
|
Emery
Sajaev
|
Stored beam, and
injection
|
2200-0400
|
BPM cogging test
|
Decker
Singh
|
Stored beam, and
injection
|
|
Wednesday, 03/06/02
|
|
|
0400-0700
|
HOM studies with hybrids fill pattern
|
Song
|
Stored beam and injection
|
0700-0800
|
Ready user beam with high emittance lattice, singlet fill pattern
|
OPS
Yao
|
Stored beam and injection
|
|
End of Studies
|
|
|