Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Monday, 08/19/02
|
|
|
0800-0830
|
Orbit data collection.
|
Singh
|
Stored beam and no injection
|
0830-1230
|
Change out circuit breaker TDP-R4-9 in building 420. (No power to SR PS during some time).
Install FORS-2 chip in a double sector
Inspect S18/29 T4 raw ps and likely replace the external interlock relay.
Replace S8BQ2 S13BV3 converters.
|
Markovich
Fors
McNamara
Puttkammer
|
No beam
|
0830-1030
|
Zones E access for replacing S31A:P1 filter comparator with a SMA-TNC patch panel
|
Erwin
|
No beam
|
0830-1030
|
Zones F access to exchange and source check the IP-100 (Gamma Probe) at RM-10
|
Vacca
|
No beam
|
0830-1030
|
Zones A access for checking 1ID P1 translation stage problem.
|
Erwin
|
No beam
|
0830-1030
|
Zones A access for checking 2ID bpm problem.
|
Kruy
Shu
|
No beam
|
0830-1030
|
Zones A access for replacing alinine films on ID3
|
Petra
|
No beam
|
0800-1030
|
Check network connection between PAR RF iocs. Change trigger source to PAR RF function generator. Need linac beam.
|
Dimonte
Sidorowizc
Johnson
|
No beam
|
1030-1230
|
Calibrate a power divider for the injector test stand. May need to reboot ioclirfgun
|
Maclean.
|
No beam
|
1230-1300
|
FORS-2 chip testing with beam
|
Fors
Maclean
|
Stored beam and injection
|
1300-1400
|
SR training
|
Hill
|
Stored beam and injection
|
1400-1500
|
Test NbBpm/DBPLD with the P1 buttons at ID21
|
Pietryla
|
Stored beam and injection
|
1500-1800
|
Setup new hybrid bunch pattern for low emittance lattice.
|
Singh
|
Stored beam and injection
|
1800-2000
|
Investigate beam loss during topup that seemed to be related to an instability
|
Harkay
|
Stored beam and injection
|
2000-2400
|
Investigate multibunch instabilities for future operational fill patterns
|
Harkay
|
Stored beam and injection
|
|
Tuesday, 08/20/02
|
|
|
0000-0500
|
Measure the response matrix and bpm history at 1mA and 3mA. Need IK5 in CW mode.
|
Sajaev
|
Stored beam and injection
|
0500-0900
|
Switch SR bpm to datapool polynomials and new gains. Check steering.
|
Emery
Shang
Singh
|
Stored beam and injection
|
0900-1200
|
Xray bpm tests.
|
Singh
Deming
Erwin
Hahne
|
Stored beam and injection
|
0900-1200
|
ID xbpm gain vs gap measurements
|
Hahne
Roberts
|
Stored beam and injection
|
0900-1200
|
Take bunch length data on linac mm-wave horn. Parallel to above SR study.
|
Decker
Borland
|
Stored beam and injection
|
1200-1300
|
SR training
|
Hill
|
Stored beam and injection
|
1300-1600
|
CPU tuning
|
Vasserman
Makarov
Emery
|
Stored beam and injection
|
1600-1900
|
Data pool correction. Adjust RTFB regulrator for optimum interaction with datapool correction.
|
Shang
Emery
|
Stored beam and injection
|
1900-2400
|
Lower emittance lattice optics steering and injection optimization
|
Emery
Sajaev
|
Stored beam and injection
|
|
Wednesday, 08/21/02
|
|
|
0000-0600
|
ID gap feedforward.
|
Decker
Singh
|
Stored beam and injection
|
0600-0700
|
Re-install the original corrector DAC chips in 2 sectors
|
Fors
|
No beam
|
0700-0800
|
Setup for User low-emittance topup.
|
OPS
|
Stored beam and injection
|