Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Monday, 6/10/02
|
|
|
0800-1100
|
10mA/30mA shielding verification for 22BM station A (low emittance singlets pattern)
|
Mohan
|
Stored beam, injection possible
|
0830-1530
|
Conditioning Linac RF
|
Pasky
|
Injection possible
|
0830-1230
|
PAR RF configuration with new VXI function generator. Can deliver beam on request.
|
Nassiri
RF
|
Injection possible
|
1100-1110
|
Acquire pulsed magnet waveforms
|
OPS
|
No beam
|
1110-1200
|
Waveguide switch to RF2/RF4
|
Horan
Nassiri
|
No beam
|
1100-1300
|
Replace the wiring to the anti-alias filters on the interleaving DSP cards, requires to turn off LTP:B1, PTB:B1, and PTB:B2
|
Fors
|
No beam
|
1110-1140
|
Remove bus-tie in 13.2 KV feeds
|
Markovich
PFS
|
No beam
|
1110-1300
|
Access zone-F (E?) to adjust 35 BPM pinhole camera vertical blades, full LOTO
|
Yang
|
No beam
|
1110-1300
|
Access Zone-A to check the space for shielding, full LOTO
|
Petra
Trakhtenberg
|
No beam
|
1200-1300
|
Reboot ID IOCs for sectors 2,4,12,14,16,22,31, & 32 to load corrected database for XBPMs.
|
M. Smith
|
No beam
|
1200-1300
|
Find cause of miscommunication between EPICS and process water PLC
processors.
|
Putnam
|
No beam
|
1200-1230
|
Install LTP:B1 beam energy PV.
|
Maclean
|
No beam
|
1200-1330
|
Repair 9BH1 Dac problem
|
Carwardine
ES group
|
No beam
|
1110-1300
|
Repair 23BP0 BPM, access zone-C, full LOTO
|
Erwin
|
No beam
|
1200-1330
|
Add database for source point calc on S16/S31. reboot iocs15bpm and iocs31bpm
|
Lenkszus
|
No beam
|
1200-1330
|
Install VME bus monitor in iocs23fb
|
Lenkszus
|
No beam
|
1330-1400
|
Restore SR beam
|
OPS
|
Stored beam and injection
|
1400-1800
|
CPU AC mode studies
|
Emery
Vasserman
|
Stored beam and injection
|
1800-2200
|
Injection efficiency studies using new BTS bpms
|
Emery
|
Stored beam and injection
|
2200-2400
|
Measure and adjust sextupoles for proper chromaticity
|
Harkay
Borland
Emery
|
Stored beam and injection
|
|
Tuesday, 6/11/02
|
|
|
0000-0600
|
High single bunch current imaging
|
Harkay
Yang
|
Stored beam and injection
|
0600-1200
|
34ID X-bpm feedback/feedforward
|
Decker
|
Stored beam and injection
|
1200-1600
|
10mA/30mA shielding verification for 22BM station C
|
Mohan
|
Stored beam and injection
|
1200-1400
|
PAR Operator test
|
Hill
Banks
|
No beam
|
1600-2000
|
Retuning of RF2 klystron
|
Horan
Nassiri
|
Stored beam and injection
|
1600-2000
|
Investigate lifetime vs tunes
|
Emery
|
Stored beam and injection
|
2000-2400
|
model-independent
analysis (MIA) technique using beam history data
|
C. Wang
|
Stored beam and injection
|
|
Wednesday, 6/12/02
|
|
|
0000-0700
|
BPM cogging test
|
Decker
|
Stored beam and injection
|
0700-0800
|
User beam with low emittance, singlets and top-up
|
OPS
Yao
|
Stored beam and injection
|