Machine Studies

Schedule for Run1-7,2003

March 10th, 0800 - March 12th, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 03/10/03

 

 

0800-0830

Collect orbit data. Mandatory refill to 100mA at 0800.

Singh

Stored beam

0730-0930

Condition and setup RF Gun 1. All studies will be done with RF Gun 1. Parasitic to collect orbit and orbit recovery.

Pasky

Limited injection

0830-0930

Switch from high to low emittance

Emery Sajaev

Stored beam and injection

0930-1300

Low emittance orbit recovery

Singh

Stored beam and injection

0900-1800

PTB bpms commissioning. Parasitic, starts as soon as RF Gun 1 is done.

Keane Zabel Erwin

Continuous injection to PTB

1130-1300

Linac training. Parasitic to orbit recovery.

OPS

Limited injection

1300-1500

Decoherence study.

CX Wang

Stored beam and injection

1300-1500

RF power monitor investigation. Parasitic to decoherence.

Grelick

 

1500-1900

Tune slope with chromaticity using beam history.

Chae Wang

Stored beam and injection

1900-2300

Xbpm tests

Hahne

Stored beam and injection

2300-2400

Bunch length measurements

Yang Harkay Chae

Stored beam and injection

 

Tuesday, 02/11/03

 

 

0000-0500

Bunch length measurements. Continued.

Yang Harkay Chae

Stored beam and injection

0500-0630

Booster requalification

OPS

No injection

0700-0900

S1 steering magnets investigation.

Fors

Stored beam

0730-0900

Linac training. Parasitic to S1 steering magnets.

OPS

Limited injection

0830-0900

Interleaving DSP reboot

Hillman

No injection

0900-1000

S3 radiation monitors replacement.

Petra

ACCESS Zone A

0900-1000

Booster main power supplies reset control line inspection

Hillman

No beam

0900-1030

Sextupole tests. Parasitic to access.

Puttkammer

No SR beam

0900-1800

PTB bpms commissioning.

Keane Zabel Erwin

Continuous injection

0900-1100

SR RF 360 Hz sidebands investigation.

Nassiri Horan

No SR beam

1000-1200

Turn off water for L6 klystron.

Dorwegt

No SR beam

1000-1200

S4 corrector regulation investigation.

Ju Wang

No SR beam

1030-1200

S40 and S1 PSCU work.

Puttkammer

No SR beam

1100-1200

S38 cavities detuning.

Nassiri Horan Harkay

No SR beam

1200-1300

S38 cavities detuning with 112 mA beam.

Nassiri Horan Harkay

Stored beam and injection

1300-1500

Low emittance injection optimization.

Emery Sajaev

Stored beam and injection

1500-1900

Datapool orbit correction.

Emery

Stored beam and injection

30 minutes

during 1500-1900

Switch back to RF Gun 2. Parasitic to datapool.

OPS Pasky

Limited injection

1900-2200

CPU perturbation measurements.

Emery

Stored beam and injection

2200-2400

Emittance with RF frequency.

Emery Sajaev

Stored beam and injection

 

Wednesday, 02/12/03

 

 

0000-0100

Emittance with RF frequency. Continued.

Emery Sajaev

Stored beam and injection

0100-0700

Local impedance measurements.

Sajaev

Stored beam and injection

1.5 hours during 0100-0700

Booster requalification.

OPS

No injection

0700-0800

Prepare for user run.

Sajaev

Stored beam and injection