Machine Studies

Schedule for Run2-10,2003

August 11th, 0800 - August 13th, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 08/11/03

 

 

0800-0830

Collect orbit data

Singh

No beam

0830-1030

Authorized access to North booster area to install equipment

Decker

No beam

0830-0930

Control access zone-B to measure 16ID X-bpms (full zone LOTO)

Hahne

No beam

0830-0900

Reboot iocleutl1 to add application

Stevens

No beam

0830-1030

Switch 420 RF system back to North feed

Markovich

No beam

0830-1030

Switch from RF1 to RF2

Grelick

RF group

No beam

0830-1230

Replace CPU firmware and test

Deriy

No beam

0830-1030

Investigate S39A:Q3 mag OT

Fors

No beam

0830-1430

Reproduce the low par accumulation fault event. Provide beam if necessary

Lewellen

PAR beam

0830-1030

To complete 23ID front end FEPS, may produce MPS trips

Friedman

Behrndt

No beam

0830-1030

Shut off water valve to allow replacement of a valve for the FOE hutch at 23-ID. Requires access to Zone-C (LOTO double sector22/23, if the valve is located in Zone-D, then only access to Zone-D is needed)

Grimmer

Bechtold

No beam

0830-1030

Control access to Zone-D to unlock 23ID shutter (LOTO double sector24/25)

Mohan

No beam

1030-1730

23 ID FEPS validation and shielding verification for 23ID

Mohan

Stored beam and injection

1430-1830

Detector test in BTS, require beam to the dump, injection possible

Decker

Sereno

Stored beam and injection

1730-1830

Control access to Zone-D to lock 23ID shutter (LOTO double sector24/25)

Mohan

No beam

1830-2230

Hybrid fill orbit restore

Singh

Yao

Stored beam and injection

2230-2400

Investigate the horizontal instability

Harkay

Stored beam and injection

 

Tuesday, 08/12/03

 

 

0000-0500

Investigate the horizontal instability

Harkay

Stored beam and injection

0500-0900

Train the crew on direct injection to booster and SR

Sereno

Stored beam and injection

0900-1100

SR re-qualification

LaBuda

 

Stored beam and injection

1100-1400

Response matrix measurement with cogging and S38A:Q1, S39A:Q1 correction

Sajaev

Stored beam and injection

1400-1600

Setup scraper for beam dump

Sajaev

Stored beam and injection

1600-1800

Train the crew on direct injection to booster and SR

Sereno

Stored beam and injection

1800-2400

ID X-bpm feedforward

Singh

Decker

Stored beam and injection

 

Wednesday, 08/13/03

 

 

0000-0630

BPM test

Singh

Erwin

Hahne

Stored beam and injection

0630-0800

Ready for 1+22 fill pattern, low emittance, and top-up

OPS

Yao

Stored beam and injection