Machine Studies

Schedule for Run2-2,2003

June 2, 1600 - June 3, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 06/02/03

 

 

1600-1700

Collect X-ray bpm reference data and align X-ray bpms

Singh

Erwin

Hahne

Stored beam and injection

1700-1900

Reboot IOCS33VP, IOCS35VP, IOCS37VP and IOCs39VP

Stein

No beam

1700-1900

Access zone-A to investigate and repair 6ID slow valve

Gagliano

No beam

1700-1900

Access zone-E to check an ion pump

Gagliano

No beam

1700-1900

Access zone- A to replace dosimeter at sector 4

Petra

No beam

1700-1800

Swap S11B:V3 convertor

Fors

PS Group

No beam

1700-1800

Access zone-E to check RTD at S31 BM

Putnam

No beam

1700-1800

Change DX9100 controllers on vacuum chamber cooling skid

Putnam

No beam

1700-2000

Access zone-A to investigate S4 undulator and remove the device if necessary

Moog

Stored beam and injection

2000-2400

SR injection transit study

Emery

Stored beam and injection

 

Tuesday, 06/03/03

 

 

0000-0300

Steering in lower emittance lattice with RF frequency

Emery

Stored beam and injection

0300-0700

Setup lower emittance lattice for singlet fill. Orbit restore for 1+22S fill pattern.

Emery

Singh

Stored beam and injection

0700-0800

Singlet fill pattern, low emittance, top-up user beam

OPS

Yao

Stored beam and injection