Machine Studies

Schedule for Run2-4,2003

June 17, 0800 - 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 06/17/03

 

 

0800-1000

Perform FEEPS-EPICS validation at 31ID

Behrndt

no beam

0800-1000

Access Zone-A to fix 5ID Gap limit switches

Grimmer

no beam

0800-0900

Reboot and test RF ioc's

DiMonte

no beam

0800-1000

Waveguide switch from RF2 to RF3, and measure heater curve

Horan

RF group

no beam

0800-0900

Investigate LOVE controllaer low flow readings in S8 and 11

Putnam

no beam

0800-0900

Refresh SF6 in Zone B of the linac

Pasky

no beam

1000-1030

Restore stored beam

OPS

Stored beam and injection

1030-1230

BPM study

Singh

Erwin

Shang

Hahne

Stored beam and injection

1230-1500

Single bunch study

Harkay

Yang

Stored beam and injection

1500-1600

Singlet fill pattern, low emittance, top-up user beam

OPS

Yao

Stored beam and injection