Machine Studies

Schedule for Run2-7,2003

July 7th, 1600 - July 8th, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 07/07/03

 

 

1600-1630

Acquire X-ray BPM reference

Decker

Stored beam and injection

1630-1730

Swap the 117MHz source in the linac

Nassiri

No injection

1630-1700

RF waveguide switch to RF4

Nassiri

No beam

1630-1730

22ID EPS/PSS system power switch

Behrndt

No beam

1630-1730

Access zone-F to replace IK2 blower

Mossison

No beam

1630-1730

Access zone-A to fix 3ID encoder

Grimmer

No beam

1630-1730

Check radiation monitor 15ID and sep Top

Vacca

No beam

1630-1730

Swap the CMPSI card on 32A:V3 and test.

Pietryla

No beam

1730-2400

1x324 fill pattern preparation

Decker

Stored beam and injection

 

Tuesday, 07/08/03

 

 

0000-0400

RTFB stability with matrix errors.

Emery

Stored beam and injection

0000-0400

Measure booster dispersion (parasitic study)

Emery

Stored beam and injection

0400-0700

Beam excitation, BPM history and imaging

Yao

Yang

Stored beam and injection

0700-0800

Ready for 1x324 fill pattern, low emittance, non-top-up beam

OPS

Yao

Stored beam and injection