Machine Studies

Schedule for Run3-11, 2003

December 2th, 1600 - December 4th, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 12/2/03

 

 

1600-1615

Record XBPM data for user orbit.

OPS

SR Beam

1615-2200

Orbit set-up for hybrid singlet mode with cogging.

Singh Decker

Stored beam and injection

2200-2400

Singlet hybrid mode with maximum single bunch current. Test with user.

Harkay Sajaev

Stored beam and injection

 

Wednesday, 12/3/03

 

 

0000-0300

Singlet hybrid mode with maximum single bunch current. Test with user (continued).

Harkay Sajaev

Stored beam and injection

0300-0500

Operator training.

OPS

No injection

0500-0700

RTFB rebooting tests.

Emery Lenkszus

Stored beam and injection

0700-0800

Beam steering in S36 cavity

Emery RF

Stored beam and injection

0800-0900

Unlock 23ID & 24ID's shutters in preparation for shielding verifications

Mohan

Access Zone-D

0800-0900

Check new BESOCM cables in the tunnel

Brill

PAR Access

0800-0900

Photograph area between L:AS2-AS3

S. Berg

Linac Access

0800-1100

Install a 60A 208Vac circuit breaker within the RF test stand breaker panel.

Trento

No beam

0800-0900

Replace Johnson controls digital input module for RF pumps 901 and 902.

Ferry

No beam

0830-0930

Replace 3ID & 4ID dosimeters under a working Warm Procedure

Petra

Access
Zone A

0830-1030

Replace blowers on S39IK2.

Morrison

Access Zone F

0900-1100

Reprogram CPU at 0900, then starting from 0930 CPU magnet tests.

Smith Emery

No beam

0900-1100

PCG Laser alignment.

Yuelin Li

Linac Access

0900-1100

23ID & 24ID PSS & EPS work, can not start until shutters are unlocked.

Hawkins

No Beam

0900-0930

Reboot IOCS21VP.

CTL

No Beam

1100-1130

Recover injector equipment and fill 10mA.

OPS

Recovery

1130-1530

Shielding Verifications 23ID & 24ID at 10mA then 30mA.

Mohan

Stored beam and injection

1130-1430

2hrs. Operator Linac training, one SR injection to 30mA during this period.

OPS

Stored beam and injection

1530-1630

Lock out the 23ID & 24ID's shutters.

Mohan

Access Zone-D

1630-1700

Recover beam.

OPS

Stored beam and injection

1700-2300

Par bunch cleaning and bunch purity vs. par rf. Fill 5mA single bunch at the end of the shift for next SR study.

Sereno Borland

Stored beam and injection

2300-2400

LEUTL for SPIRIT operation.

Lewellen

Infrequent injection possible

 

Thursday, 12/4/03

 

 

0000-0330

LEUTL for SPIRIT operation (continued).

Lewellen

Infrequent injection possible

2300-0330

Single bunch motion imaging. Parallel to LEUTL.

Yang Chae

Stored beam

0330-0530

Operator training.

OPS

No injection

0530-0730

S35 bpm noise study.

Lenkszus Laird Erwin singh

Stored beam and injection

0730-0800

Ready for 1+8X7 fill pattern, low emittance, TopUp, cogging

OPS

Stored beam and injection