Machine Studies

Schedule for Run3-12, 2003

December 9th, 0800 - December 9th, 1600

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 12/9/03

 

 

0800-0815

Record XBPM data for user orbit.

OPS

SR Beam

0815-0900

Install Timing card in iocmtime for SR pre-trigger to A014.

Lenkszus

Risk of beam loss

0815-0830

RF work.

RF group

Possible beam loss

0815-0900

FE EPS software changes in Sector 9.

Behrndt

Risk of beam loss

0900-1000

Test MXI/VXI fix for power PC processor in Booster BPM iocbbpm1

Lenkszus

Injection available

0830-1030

CPU fast ramp tests. Parallel to timing card, FE EPS, etc.

Emery Smith

Stored beam and injection

1030-1330

Gap scans.

Decker

Stored beam and injection

1330-1500

OAG presentation.

OAG

Stored beam and injection

1500-1600

Ready for 1+8x7 hybrid fill pattern, topup, cogging, 8mA in the main bunch.

Sajaev OPS

Stored beam and injection