Machine Studies

Schedule for Run3-3,2003

October 13, 0800 - October 15, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 10/13/03

 

 

0800-0820

Acquire BPM reference data

Singh

Stored beam and injection

0800-0820

Acquire SR pulsed waveforms

Jones

Stored beam and injection

0830-1030

Access to Zone-E to test S35B:P1, LOTO double sector 34/35

Keane

Gold

No beam

0830-1030

Access to Zone-A to replace an encoder on 3ID

Grimmer

No beam

0830-0930

Remove monitoring equipment at 9ID front end EPS

Behrndt

M. Smith

No beam

0830-1130

Check and readjust as

necessary linac VSWR blanking in the various switched linac modes (occasional injection possible)

Grelick

No beam

0830-0930

Investigate ioc communication problem

Gunderson

No beam

0830-1130

Troubleshoot the fiber line providing the CPU AC mode switch trigger (

Deriy

No beam

0830-1030

Test Ethernet dual redundant 100/10 media converter with an sr vp and

bpm iocs

Lenkszus

No beam

0830-1030

Look into the EMW supply leaking problem

McNamara

No beam

0830-0930

Replace blowers on RTFB iocs

Gold

No beam

0830-0930

Swap out S23A:V2 Dac board due to readback problem

Fors

PS group

No beam

0830-1230

Troubleshoot B:IK noise problem

Hillman

No beam

1130-1530

Tune measurement and bunch cleaning study in the PAR

Sereno

Stored beam and injection

1230-1430

SR requalification

Schroeder

Stored beam and injection

1430-1830

Test 35BP1 and 35BP2 BPMs

Erwin

Lill

Stored beam and injection

1500-1830

linac training

Keyser

Stored beam and injection

1830-2300

Booster direct injection BPM test

Lill

Stein

Sereno

Stored beam and injection

2300-2400

Injector training (2300-0700 13- 14)

Flood

Stored beam and injection

 

Tuesday, 10/14/03

 

 

0000-0800

Orbit recovery

Singh

Decker

Stored beam and injection

0000-0800

Commission and test booster vertical injection controllaw

Sereno

Stored beam and injection

0800-1000

Access zone-F to replace cavity blowers.

Bromberek

 

No beam

0800-1000

Remove a waveguide plate on RF1

Nassiri

 

No beam

0800-1000

Control access to Zone-D to remove locks on 23ID front end shutters, check operational readiness

Mohan

Friedman

Behrndt

No beam

0800-1300

L1 klystron conditioning (injector available)

Pasky

Injector available

1000-1200

10mA shielding verification of 23ID

Mohan

Stored beam and injection

1200-1400

30mA shielding verification of 23ID

Mohan

Stored beam and injection

1300-1500

Linac qualification

Shumard

Stored beam and injection

1400-1500

Control access to Zone-D to put locks on 23ID front end shutters

Mohan

No beam

1500-1700

SR requalification test

Weyer

Stored beam and injection

1700-1830

Linac operator training

Keyser

Stored beam and injection

1700-2100

RTFB config. study

Singh

Decker

Stored beam and injection

2100-2400

Transient beam response for MIA analysis

Chae

C. Wang

Stored beam and injection

2300-2400

Injector training (injection may be needed)

Flood

Stored beam and injection

 

Wednesday, 10/15/03

 

 

0000-0100

Transient beam response for MIA analysis

Chae

C. Wang

Stored beam and injection

0100-0400

BTS optics/trajectory investigation

Emery

Stored beam and injection

0400-0700

Check RTFB feedback matrix with gain included

Emery

Stored beam and injection

0700-0800

Ready for 0+24x1 fill, top-up and cogging

OPS

Yao

Stored beam and injection