Schedule for Run04-2, 2004

February 2th, 1600 - February 3rd, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 2/2/04

 

 

1600-1615

Record XBPM data for user orbit

OPS

Stored beam and injection

1615-1715

bpm database for 24 bunch fill

 

Singh

Decker

Stored beam and injection

1715-1800

Re-measure response matrix

Yao

Stored beam and injection

1800-2100

Xbpm alignment (parasitic)

Hahne

 

1800-2400

ID xbpm feedforward

Decker

Singh

Stored beam and injection

 

Tuesday, 2/3/04

 

 

0000-0300

Beta function correction, close gaps and check X-ray BPM data

Sajaev

Stored beam and injection

0300-0500

Ring energy aperture measurement

Borland

Emery

Stored beam and injection

0500-0700

IS1 leakage field compensation

Borland

Emery

Stored beam and injection

0700-0800

Ready for 0+24X1 fill pattern, low emittance, TopUp

OPS

Stored beam and injection