Schedule for Run01-6, 2004

March 1st, 1600 - March 2nd, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 3/1/04

 

 

1600-1615

Record XBPM data for user orbit

OPS

Stored beam and injection

1615-1700

Inject with new fill pattern and adjust machine parameters

Sajaev

Yao

Stored beam and injection

1615-1700

Replace BI SMA connector at the back of the chassis for 19BP0

Erwin

No impact

1615-1700

Replace BO SMA connector at the back of the NbBPM chassis for 3BP0

Erwin

No impact

1700-2000

CPU linear mode perturbation measurement

Emery

Vasserman

Stored beam, no injection

2000-2100

CPU trigger signal hardware test

Deriy

Xu

Stored beam, no injection

1700-2100

Photocathode gun tune check and possible removal for repair. Authorized Access into Linac

Lewellen

No
Injection

2100-2400

Recover user orbit

Singh

Decker

Limited injection

2300-2400

Linac/PAR Operator training between 23:00-07:00

Forth

Limited injection

 

Tuesday, 3/2/04

 

 

0000-0100

Recover user orbit

Singh

Decker

Limited injection

0000-0100

Linac/PAR Operator training between 23:00-07:00

Forth

Limited injection

0100-0700

Energy aperture studies with modified lattice

Emery

Borland

Stored beam and injection

0700-0800

Ready for 0+324X1 fill pattern, low emittance, non-TopUp

OPS

Stored beam and injection