Machine Studies

Schedule for Run2-1,2004

May 20 0800 to May 25 0800

 

Time

Descriptions

Studiers

SRStatus

 

Thursday, 05/20/04

 

 

0800-1400

Lattice setup and initial beam store. Beta functions measurement.

Emery Sajaev

 

Stored beam and injection

1000-1200

Initial pinhole camera setup. Parasitic to the lattice setup, as soon as beam is stored with enough current.

Yang

Stored beam and injection

1400-1800

RFBPM tests.

RTFB tests.

Singh Erwin Bui Decker Lenkszus

Stored beam and injection

1300-1500

Linac training. Parallel to lattice setup and bpm tests.

Grodecki

Limited injection

1800-2400

BPM offsets.

Singh

Stored beam and injection

2000-2200

Linac training. Parallel to BPM offsets.

Glenn

Limited injection

 

Friday, 05/21/04

 

 

0000-0800

Direct injection and 1296 bunches fill.

Sereno

Stored beam and injection

0600-0800

Determine optimum timing of BTS bpms for 1296 mode injection. Parallel to direct injection.

Sereno, Emery Lill

Stored beam and injection

0800-1400

BPLD validation.

Pietryla Bui

Stored beam and injection

1200-1400

Linac training. Parallel to BPLD validation.

Grodecki

Limited injection

1400-1800

ID xbpm tests.

Hahne

Stored beam and injection

1800-2200

BM xbpm tests.

Hahne

Stored beam and injection

2000-2200

Linac training. Parallel to xbpm tests.

Glenn

Limited injection

2200-2400

Beta function correction and 324 bunches mode setup.

Sajaev

Stored beam and injection

 

Saturday, 05/22/04

 

 

0000-0100

Beta function correction (continued).

Sajaev

Stored beam and injection

0100-0700

Orbit recovery.

Singh

Stored beam and injection

0700-0900

DBPLD beam status studies.

Pietryla Bui

Stored beam and injection

0900-1300

Remove BP1 SCDU (sectors 3-6). Move beam history modules.

Pietryla Lenkszus

Stored beam and injection

1300-1500

Various software tests

Emery

Stored beam and injection

1300-1500

Linac training. Parallel to software tests.

Glenn

Limited injection

1500-1900

Check proper functioning of bpm histories for MPS dumps.

Emery

Stored beam and injection

1900-2400

ID xbpm feedforward

Decker

Stored beam and injection

 

Sunday, 05/23/04

 

 

0000-0300

ID xbpm feedforward (continued).

Decker

Stored beam and injection

0300-0900

Transverse single bunch instability study.

Harkay

Stored beam and injection

0900-1300

CPU coupling correction.

Emery

Stored beam and injection

1300-1600

Characterize injection septum flag and optimize efficiency.

Emery

Stored beam and injection

1600-2000

Investigate orbit disturbance during steering.

Emery

Stored beam and injection

1800-2000

Linac training. Parallel to orbit disturbance investigation.

Glenn

Limited injection

2000-2400

Install and test longitudinal damping lattice.

Harkay Guo

Stored beam and injection

 

Monday, 05/24/04

 

 

0000-0500 or shorter

Instability study in 1296 bunches mode

Harkay

Stored beam and injection

0500-0800

Simulate lower bit resolution in RTFB loops.

Emery Lenkszus

Stored beam and injection

0800-1200

Klystron operating efficiency study at 103mA.

Horan Nassiri

Stored beam and injection

0800-1000

Final pinhole camera setup. Parallel to klystron studies.

Yang

Stored beam and injection

1200-1300

23ID shielding verification at 30mA.

Ramanathan

Stored beam and injection

1300-1700

Program changes and reverification of 9BM.

Behrndt

No SR beam

1300-1500

Linac training. Parallel to 9BM reverification.

Leeson

 

1300-1500

Booster training. Parallel to 9BM reverification.

Forth

 

1700-2100

Create ID30 and septum bump for ID3/4 protection.

Emery

Stored beam and injection

2100-2400

Canted undulator xbpm feedforward.

Decker

Stored beam and injection

 

Tuesday, 05/25/04

 

 

0000-0500

Canted undulator xbpm feedforward (continued).

Decker

Stored beam and injection

0500-0700

Injection efficiency test with gaps

Yao

Stored beam and injection

0700-0800

Ready user beam with low emittance, 1x324 fill pattern and non-topup

Yao

OPS

Stored beam and injection