Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Tuesday, 8/10/04
|
|
|
0800-0805
|
Record XBPM data for user orbit with TopUp running. Keep the beam at the end.
|
OPS
|
SR Beam
|
0805-1000
|
Test operation of the PAR harmonic power amplifiers.
|
Grelick
|
Limited injection
|
0805-1000
|
Operator training - Linac. Parallel to PAR rf work.
|
Leeson
|
Limited Inj
|
0805-0930
|
S40 cavity 4 tuner repair.
|
RF group
|
ACCESS Zone F
|
0805-1000
|
SCR testing. Parallel to PAR rf work.
|
Borland Shang
|
|
1000-1200
|
PAR bunch cleaning test.
|
Sereno Borland Yao
|
Stored beam and injection
|
1200-1330
|
Test orbit controllaw despiking reramping.
|
Borland Shang
|
Limited injection
|
1200-1330
|
Operator training - Linac. Parallel to despiking reramping.
|
Gagliano
|
Limited injection
|
1330-1500
|
RTFB tests.
|
Singh Lenkszus
|
Stored beam and injection
|
1500-1600
|
Ready for 0+24X1 fill pattern, low emittance, TopUp
|
OPS
|
Stored beam and injection
|