Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Monday, 6/28/04
|
|
|
1600-1605
|
Record XBPM data for user orbit with TopUp running.
|
OPS
|
SR Beam
|
1605-2000
|
Install and correct new ID30 increased dispersion lattice.
|
Sajaev
|
Stored beam and injection
|
1630-1830
|
Operator training - PAR. Parallel to ID30 lattice work.
|
Glenn
|
Limited Inj
|
2000-2400
|
Characterize radiation effects of ID30 lattice.
|
Borland Emery
|
Stored beam and injection
|
|
Tuesday, 6/29/04
|
|
|
0000-0300
|
Punch down quads in S38-S39. Install beta correction, recover the lifetime.
|
Sajaev
|
Stored beam and injection
|
0300-0700
|
Investigate bunch purity with RG1 and RG2.
|
Sereno
|
Stored beam and injection
|
0700-0800
|
Ready for 0+24X1 fill pattern, low emittance, TopUp
|
OPS
|
Stored beam and injection
|