Machine Studies
Schedule for Run03-2, 2004
October 11th, 1600 - October 12th, 0800
Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Monday, 10/11/04
|
|
|
1600-1605
|
Record XBPM data for user orbit
|
OPS
|
Stored Beam
|
1605-1635
|
Waveguide switch to RF3 & RF4 providing
|
RF Group
|
No Beam
|
1635-1930
|
Set-up 0+24*1 lattice & SR Injection Efficiency Studies
|
Yao, Schroeder
|
Stored Beam & Inj
|
1930-2200
|
Orbit Recovery
|
Decker, Singh
|
Stored Beam & Inj.
|
1930-2130
|
Par Instability Investigation (Parasitic)
|
Yao
|
Inj. Avail.
|
2200-2300
|
Test SR CW drive for Xbpm Response Measurement (Parasitic)
|
Yao
|
Stored Beam
|
2200-2300
|
Operator training
|
Glenn
|
Limited Inj
|
2300-2400
|
Measurement of transverse wake kick due to vertical scraper
|
Borland
|
Stored Beam & Inj
|
|
Tuesday, 10/12/04
|
|
|
0000-0300
|
Measurement of transverse wake kick due to vertical scraper
|
Borland
|
Stored Beam & Inj
|
0300-05:30
|
Collect HOM damper data
|
Harkay
|
Stored Beam & Inj.
|
0530-0700
|
Testing Orbit Configuration
|
Singh
|
Stored Beam
|
0700-0800
|
Ready for 0+24X1 fill pattern, low emittance, TopUp
|
OPS
|
Stored Beam & Injection
|