Schedule for Run03-3, 2004

October 18th, 0800 - October 20th, 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 10/18/04

 

 

0800-0805

Record XBPM data for user orbit with TopUp running

OPS

Stored Beam

0805-1400

Reconfigure waveguide to Bldg. 420 RF Teststand

RF Group

No Beam

0805-1000

Test dual redundant ethernet transceiver

module. Will power cycle iocs1fb

Lenkszus

No Beam

0805-1200

Change the charging resistor to a lower value in B:EK:PS

Puttkammer

No Beam

0805-1000

Test 2 RS-422 IP carrier boards using an active field bus link on iocs40misc

Stevens

 

0805-0900

Interleaving PS DSP reboots

Hillman

No Beam

0805-1000

Check out spare SCR regulator cards at RF5.

Nassiri

 

No Beam

0805-1000

Inject beam into PAR with L2 down and L3 providing power to investigate energy spread due to power fluctuation.

Nassiri/Pasky

No Beam

0830-1130

Diagnose problem with PS1 in sector 24 ID

Wiemerslage/Ramanathan

Access
Zone D

0830-0845

Review Status of 23ID DS gearbox leak

Kasa

Access

Zone D

0900-1100

Replace S38, Cav. #2 Blower

Pace,

McKenzie

Access
Zone F

0930-1030

Replace ID dosimeters S3-4

Petra

Access
Zone A

0930-1030

Swap filter comparator for 8AP3

Erwin

Access
Zone A

1000-1200

Look into a faulty status/relay board on L1RG2 LFA TRIM

Puttkammer

No Inj

1000-1100

Move ID bpm blade gain compensation for ID gap from Legacy PVs to msAve PVs for ID19 and ID20. Affects iocs19fb which will be rebooted

Lenkszus

No Beam

1000-1300

Measure SLEDs at L2, L4 and L5 to investigate power fluctuation.

Nassiri

No Beam

1030-1230

Access to check possible water leak at 33-BM

Dortwegt

Access
Zone E

1030-1230

Attach rtd elements and readout cables to S35 Pinhole Camera

Putnam

Access Zone E

1100-1300

Set Up Pinger Power Supply

Yao, Sun,

No Beam

1100-1200

Investigate a problem Glenn Decker has observed with datapool orbit correction and some ID x-ray bpms

Lenkszus

 

1330-1400(?)

Measure RF4 klystron focus current and adjust if necessary(after RF LOTO release)

Bromberek

No Beam

1330-1400(?)

Booster RF5 measurement (after RF LOTO release)

Bromberek

No Beam

1300-1500

Setup new hardware for PAR bunch cleaning

Grelick/Yao

No Linac/PAR beam

1300-1400

Determine extra fundamental cavity field probe availability for use with bunch cleaning.

Smith

PAR Access

1400-1500

RF Phase studies

Erwin/Pasky

No Beam

1500-1800

Bunch cleaning test

Yao, Sereno

Stored Beam & Inj.

1800-2100

PAR instability study (parasitic)

Yao, Yang

Inj. possible

1800-2400

Canted undulator xbpms

Decker

Stored beam & Lim. inj

2100-2300

Operator training-Booster (1500-2300)

Grodecki

Limited Inj

 

Tuesday, 10/19/04

 

 

0000-0200

Canted undulator xbpms

Decker

Stored beam & Lim. inj.

0000-0200

Operator training Booster (2300-0700)

Glenn

Limited Inj

0200-0600

Unannounced studies

Sajaev

Stored Beam & Inj.

0600-0900

SR injection efficiency improvement

Yao/Sajaev/Emery

Stored Beam & Inj.

0900-1200

Measure Xbpm response

Diag/Yao/Lenkszus

Stored beam & Inj.

1200-2000

Xbpm alignment shift

Decker/Diag

Stored Beam & Inj.

1200-1800

SR top-up with bunch cleaning (parasitic)

Yao, OPs

Stored Beam & Inj.

2000-0000

Vertical kicker induced beam motion

Yang, Guo, Harkay

Stored beam & Lim. Inj.

1900-2100

Operator training-Booster 1500-2300

Grodecki

Limited Inj

 

Wednesday, 10/20/04

 

 

0000-0200

Vertical kicker induced beam motion

Yang/Guo/Harkay

Stored beam & Lim. inj.

0000-0200

Operator training-Booster 2300-0700

Glenn

Limited inj.

0200-0500

Install P0 and P1 offsets

Singh/Bui

Stored beam

0500-0700

17bm and 19bm steering tests

Hahne/Singh

Stored beam

0700-0800

Ready for 0+24X1 fill pattern, low emittance, TopUp

OPS

Stored Beam & Injection