Machine Studies

Schedule for Run03-4, 2004

October 26th, 0800 - 1600

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 10/26/04

 

 

0800-0805

Record XBPM data for user orbit with TopUp running

OPS

Stored Beam

0805-0830

Replace VTM200revB with VTM200revC at iocs1bpm to correct a problem that occurs at power up. This will require powering down iocs1bpm. VTM200 is the Ethernet media convertor transceiver.

Laird

No Beam

0805-0830

Pull out the E-Stop button on the upstream insertion device 23ID

OPS

Access
Zone D

0805-0830

Switch to K2 down mode next Tuesday and operate with K3 during study period to tune L2 klystron parameters to minimize frequency sidebands.

Nassiri, Pasky

No Beam

0805-0830

Make correction to database that handles write permission for BTS dipole setpoints. Reboot iocbvp3 test.

Varotto, Flood

No Beam

0830-1030

Check injection efficiency

Emery/ Sajaev

Stored Beam & Injection

1030-1230

HOM studies

Nassiri/Harkay

Stored Beam & Lim. Inj.

1030-1330

PAR Vertical instability study

Chae/Yao/Yang

Limited Inj.

1230-1430

Xbpm test for ID2,3,14 and BM17

Singh/Hahne

Stored Beam

1330-1500

Operator Training - Booster(0700-1500)

D.Glenn

Lim. Inj.

1500-1600

Ready for 0+24X1 fill pattern, low emittance, TopUp

OPS

Stored Beam & Injection