Machine Studies

Schedule for Run1-4,2005

February 22 0000 to February 22 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 02/22/05

 

 

0000-0100

Swap out power supply for iocs39vp

Varotto

No SR beam

0100-0200

Recalibrate S39 scraper

Stevens

No SR beam

0000-0200

PAR phase scan

Yao Yang

No injection

0200-0300

Adjust kicker timing

Sajaev

Stored beam and injection

0300-0700

Correct beta functions and minimize coupling

Sajaev

Stored beam and injection

0615-0645

L2 SLED cooling water repairs. Parallel to coupling.

Theres

No injection

0700-0800

Prepare for user beam. 24 singlets, topup.

OPS

Stored beam and injection