Machine Studies

Schedule for Run02-4, 2005

June 20th 0800 - June 21st 0800

 

Time

Descriptions

Studiers

SRStatus

 

Monday, 6/20/05

 

 

0800-0805

Collect XBPM orbit data

OPS

Stored Beam & Injection

0805-0900

Swap sector 38 RF cavity 3 & 4 ion gauge cables

RF Group

No Beam

0805-0900

Investigate Kalmus problems

RF Group

No Beam

0805-0900

PSS End-to-End test at 11-BM and 30-ID

SI Group

No Beam

0805-0830

Replace board in IOCID30 & reboot

M. Smith

No Beam

0805-0830

Switch to PAR RF Harmonic System #2

OPS

No Beam

0805-0900

Inspect RF waveguide switches

RF group

No Beam

0805-0825

reboot iocmtime & ioclibpm2

Lenkszus

No Beam

0805-0900

Attempt to generate a mis-setting of S23C:H1

Emery

No beam

0805-0900

Tie in 30ID EPS

McNamara

No Beam

0830-0900

Tune up with PAR RF Harmonic System #2

CY Yao

 

0900-1200

Par instability at high rf12 AGC setting (days)

T. Smith, CY Yao, Y. Chae

Occasional Injection

0900-1100

11-BM-A shielding verification

Ramanathan

Stored beam

1100-1500

Replace bm xbpm filterless modules

Hahne, Roberts, Singh

Stored beam

1200-1400

Linac Training

Poncin

Limited Injection

1400-1600

Test modified 9.77 MHz source (days or evenings) Storage ring needed the last hour

A. Grelick, CY Yao

Stored Beam & Injection

1600-1700

Test the SR bunch current monitor attenuator interface

CY Yao, Gold

Stored Beam & Inj.

1700-2300

16mA singlet study

Harkay, Sajaev, Chae, Guo, Borland, Emery, Lumpkin, Yang

Stored beam & injection

2300-2400

HOM damper studies

Harkay, Nassiri, Waldschmidt, Bromberek, Emery

Stored beam & injection

 

Tuesday, 6/21/05

 

 

2400-0200

HOM damper studies

Harkay, et al

Stored beam & Injection

0200-0300

test SRBunchTrain and SRTopupBucketAssignment using new PVs

Emery

Stored beam & Injection

0400-0700

Linac phase controllaw studies

Sereno

Occ. Inj. Available

0300-0700

Orbit restore and collect idfeedforward data

Singh

Stored Beam

0700-0800

Prepare for user beam

OPS

Stored Beam & Inj.