Machine Studies

Schedule for Run02-5, 2005

June 28th 0000 - June 28th 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 6/20/05

 

 

0000-0010

Collect XBPM orbit data

OPS

Stored Beam & Injection

0010-0500

ID xbpm studies

Decker

Stored Beam & Occ. Inj.

0010-0430

Par bunch length measurement and tunerFF optimization

Yao

Occ. Inj. Available

0430-0500

Prepare for Linac/PAR Access (Authorized Access, Full LOTO)

OPS

Linac/PAR Access

0500-0630

Investigate/repair in-tunnel water leak

ME Group

Linac/PAR Access

0630-0700

Recover Linac/PAR beam

OPS

No injection

0500-0700

Replace S27 GESPAC

Sprau

No Beam

0500-0630

Reboot interleaving DSPs/Standardize interleaving magnets

Hillman/ OPS

No Injection

0600-0700

Test L2PM3 hardware (no Linac steering controllaw during this time)

Gold

 

0630-0700

Replace MPCs in sector 32-4 & sector 39-2

Vacuum Grp

No stored beam

0700-0730

Connect Johnson Controls for CNM project

PFS

Possible Impact to Beam

0700-0800

Prepare for User Beam 0+24*1 Top-Up

OPS

Stored Beam & Injection

0730-0800

Collect XBPM orbit data #2

OPS

Stored Beam & Injection