Machine Studies

Draft Schedule for Run01-2, 2006

February 7th 0700 - February 8th 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 2/7/06

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0830-0930

1 hr LTP ControlLaw training

LaBuda

Injection possible/ No Top Up

0810-1000

Measure water flows for currently unmonitored flows of pinhole slits and pinhole camera

Yang/Dortwegt

No beam

0810-0830

Reboot SR VP IOCs

Varotto

No Beam

0810-1000

Install boards/cover plates on bake-out skids (Utility aisle

Hoyt/Dortwegt

No beam

0810-1100

B:BM:PS Investigation & testing (may not be able to provide beam during first hour, occasional injections may be possible with notice)

P.S. Group/Sereno

No injection

0810-0915

PSS end to end test

Friedman

No Beam

0810-1000

Install dosimeters on RF4 troubleshoot RF4 supply temperature

Horan

No Beam

0810-1000

xbpm cable pull in ID32

Hahne/Gold

Beam possible

0810-0815

Archive SR Kicker and Septum Waveforms

OPS

No Beam

0815-1000

Check IK1 timing

Hillman

No beam

0900-1000

check conditioning validity PVs.

Soliday/Emery

No beam

0930-1030

1 hr Validate EMI supply & adjust L4

Pasky/Cours

Limited Injection

1000-1005

Store 102mA

OPS

Injection needed

1000-1200

bpms test and training

Singh/Diag

Stored beam

1100-1500

test PAR rf12 gap voltage control loop.

Grelick, T. Smith, Yao

Limited Injection after 1400

1400-1700

shielding verification of 14-ID-C station and transport (10 ma for 1 hr and 30 ma for two hrs)

Ramanathan

Stored beam Occ. Inj.

1500-1530

Test the bunch current baseline pem

Yao, Shang

Stored beam Occ. inj.

1700-2100

install new P0 BPM gains

Sajaev, Lenkszus, Singh

Vadim

Stored beam & injection

2100-2400

check injection efficiency problems.Aalso take cerenkov data from tek DPO scope

Emery/Sajaev

Stored beam & Injection

 

Wednesday, 2/8/06

 

 

0000-0200

check CPU correction.

Emery

Stored Beam

0200-0400

SR training (2300-0700)

S. Flood

Stored Beam & Injection

0400-0700

xbpm data collection

Decker

Stored beam & Top-Up

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection