Machine Studies

Schedule for Run02-1, 2006

May 23rd 0800 - May 30th 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 5/23/06

 

 

0800-0830

SR RF Waveguide Switch

RF Group

No beam

0800-0900

Booster switchgear repair

PFS

No beam

0800-0900

Reboot SR VP IOCs

Quock

Limited Injection

0800-1000

Final verification of Linac arc detector

Grelick

No Injection

0800-1100

Test RF1 PLC logic

Horan

No Beam

0830-0900

RF2 MPS Validation

RF Group/M. Smith

No Beam

0900-1100

PAR RF gain balancing

Grelick

No Injection

1100-1300

RF BPM tests.

Erwin

Stored beam

1100-1300

Linac PEM upgrade. Parallel to RF BPM tests.

Pasky Soliday

Limited SR injection

1300-1700

Optimize injection.

Emery Sajaev

Stored beam & injection

1700-2100

SR BPM system tests.

Singh

Stored beam

1700-2100

BTS emittance and OTR/ODR experiments.

Sereno

Limited SR injection

2100-2300

Test new booster injection controllaw.

Sereno

Stored beam & injection

2300-2400

Correct beta functions.

Sajaev

Stored beam & injection

 

Wednesday, 5/24/06

 

 

0000-0300

Correct beta functions (continued).

Sajaev

Stored beam & injection

0300-0500

SR training.

S. Flood

Stored beam & injection

0500-0700

OPEN

 

 

0700-0900

RF1 cavity multipacting test.

Yao Chae

No injection

0830-0900

Connect new bunch current monitor Reboot of iocsrtune (no adjustments to bunch current monitor can be made until 1500)

Varotto/Lenkszus

No impact

0830-0900

420 RF Waveguide Switch

RF Group

No beam

0900-1100

BPLD alarm validation.

Bui Shang

Stored beam & injection

1100-1500

SR DC/AC orbit controllaw tests.

Singh Lenkszus Shang

Stored beam & injection

1100-1400

Check P0 feedback signal. Parallel to controllaw tets.

Yao

Stored beam

1430-1500

Connect old bunch current monitor & reboot of iocsrtune

Varotto/Lenkszus

No impact

1500-1900

BTS emittance and OTR/ODR experiments.

Sereno

Limited SR injection

1500-1900

Test BM xbpms.

Hahne

Stored beam

1900-2100

Test PAR harmonic rf tube amplifier.

Yao Grelick

Stored beam & injection

2100-2400

Measure P1 offsets.

Bui OPS

Stored beam & injection

 

Thursday, 5/25/06

 

 

0000-0300

Measure P1 offsets (continued).

Bui OPS

Stored beam & injection

0300-0500

SR training.

S Flood

Stored beam & injection

0500-0700

Collect rtfb data.

Sun

Stored beam & injection

0700-0900

Investigate P1/P0 rms.

Lenkszus Singh Sun

Stored beam & injection

0900-1100

PEM testing.

OPS

Stored Beam & Injection

1100-1500

Test S19 hard x-ray bpm. Shutter support required.

Singh Hahne Rosenbaum

Stored Beam & Injection

1500-1700

Install P1 offsets.

Bui

Stored Beam & Injection

1700-2100

Validate bplds.

Bui

Stored Beam & Injection

2100-2300

Booster training.

Poncin

Limited Injection

2300-2400

SR training.

S. Flood

Stored Beam & Injection

 

Friday, 5/26/06

 

 

0000-0100

SR training.

S. Flood

Limited Injection

0100-0400

Intra girder beam based measurements.

Emery

Stored Beam & Injection

0400-0800

ID xbpm tests.

Hahne

Stored Beam & Injection

0800-1600

PSS validations

SI group

No beam

0800-1600

Various 420 RF system studies/tests

RF Group

No beam

0800-0830

Prepare for Zone F Access

OPS/PFS

No beam

0830-0930

installing a different CPU board in iocinjtime

Lenkszus

No beam

0830-0930

Repair/replace RF cavity IR detector

Morrison

Zone F access

0900-1030

Document the configuration for the new septum regulators if Booster & SR (Septums off)

Hillman/Puttkammer

No injection

1600-1800

Booster training.

Poncin

Limited Injection

1800-2200

PAR fundamental phase modulation.

Yao Grelick

Stored Beam & Injection

2200-2400

Characterize new sextupoles.

Sajaev

Stored Beam & Injection

 

Saturday, 5/27/06

 

 

0000-0200

Characterize new sextupoles (continued).

Sajaev

Stored Beam & Injection

0200-0800

Optimize vertical kick for high intensity.

Harkay

Stored Beam & Injection

0800-1000

Collect FF data.

Singh

Stored Beam & Injection

1000-1400

Investigate P1/P0 rms.

Singh Sun

Stored Beam & Injection

1400-1600

Collect hybrid fill intensity.

Sun

Stored Beam & Injection

1600-2200

Orbit recovery.

Singh

Stored Beam & Injection

1700-1900

Booster training.

Poncin

Limited Injection

2200-2400

OPEN

 

 

 

Sunday, 5/28/06

 

 

0000-0400

OPEN

 

 

0400-0600

Optimize vertical kick for high intensity.

Harkay

Stored Beam & Injection

0600-1000

set up pinhole camera and bunch purity monitor for the user run

Yang

Stored Beam & Occ. Inj.

1000-1400

Routine tests of SR PEM steering software

Emery

Stored Beam & Injection

1400-1800

Characterize each undulator effect on coupling and lifetime.

Emery

Stored Beam & Injection

1800-2000

Check encoders

Merritt

No Beam

1800-2000

Booster training.

Poncin

Limited Injection

2000-2400

Multibunch bursting instability investigation.

Harkay

Stored Beam & Injection

 

Monday, 5/29/06

 

 

0000-0200

Multibunch bursting instability investigation (continued).

Harkay

Stored Beam & Injection

0200-0700

OPEN

 

 

0700-1100

Operational orbit controllaw test with topup

Singh

Stored beam & injection

1100-1500

Check out CPU compensation.

Emery

Stored Beam & Injection

1500-1900

BPM prototype software tests.

Emery Pietryla

Stored Beam & Injection

1900-2100

Setup PAR and bunch cleaning system.

Yao

Stored Beam & Injection

2100-2400

Checking encoders

Merritt

No beam

 

Tuesday, 5/30/06

 

 

0000-0100

Checking encoders

Merritt

No beam

0100-0500

HOM measurements.

Harkay

Stored Beam & Injection

0500-0630

OPEN

 

 

0630-0800

Ready for TopUp 0+24*1

OPS

Store Beam & Injection