Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Tuesday, 5/23/06
|
|
|
0800-0830
|
SR RF Waveguide Switch
|
RF Group
|
No beam
|
0800-0900
|
Booster switchgear repair
|
PFS
|
No beam
|
0800-0900
|
Reboot SR VP IOCs
|
Quock
|
Limited Injection
|
0800-1000
|
Final verification of Linac arc detector
|
Grelick
|
No Injection
|
0800-1100
|
Test RF1 PLC logic
|
Horan
|
No Beam
|
0830-0900
|
RF2 MPS Validation
|
RF Group/M. Smith
|
No Beam
|
0900-1100
|
PAR RF gain balancing
|
Grelick
|
No Injection
|
1100-1300
|
RF BPM tests.
|
Erwin
|
Stored beam
|
1100-1300
|
Linac PEM upgrade. Parallel to RF BPM tests.
|
Pasky Soliday
|
Limited SR injection
|
1300-1700
|
Optimize injection.
|
Emery Sajaev
|
Stored beam & injection
|
1700-2100
|
SR BPM system tests.
|
Singh
|
Stored beam
|
1700-2100
|
BTS emittance and OTR/ODR experiments.
|
Sereno
|
Limited SR injection
|
2100-2300
|
Test new booster injection controllaw.
|
Sereno
|
Stored beam & injection
|
2300-2400
|
Correct beta functions.
|
Sajaev
|
Stored beam & injection
|
|
Wednesday, 5/24/06
|
|
|
0000-0300
|
Correct beta functions (continued).
|
Sajaev
|
Stored beam & injection
|
0300-0500
|
SR training.
|
S. Flood
|
Stored beam & injection
|
0500-0700
|
OPEN
|
|
|
0700-0900
|
RF1 cavity multipacting test.
|
Yao Chae
|
No injection
|
0830-0900
|
Connect new bunch current monitor Reboot of iocsrtune (no adjustments to bunch current monitor can be made until 1500)
|
Varotto/Lenkszus
|
No impact
|
0830-0900
|
420 RF Waveguide Switch
|
RF Group
|
No beam
|
0900-1100
|
BPLD alarm validation.
|
Bui Shang
|
Stored beam & injection
|
1100-1500
|
SR DC/AC orbit controllaw tests.
|
Singh Lenkszus Shang
|
Stored beam & injection
|
1100-1400
|
Check P0 feedback signal. Parallel to controllaw tets.
|
Yao
|
Stored beam
|
1430-1500
|
Connect old bunch current monitor & reboot of iocsrtune
|
Varotto/Lenkszus
|
No impact
|
1500-1900
|
BTS emittance and OTR/ODR experiments.
|
Sereno
|
Limited SR injection
|
1500-1900
|
Test BM xbpms.
|
Hahne
|
Stored beam
|
1900-2100
|
Test PAR harmonic rf tube amplifier.
|
Yao Grelick
|
Stored beam & injection
|
2100-2400
|
Measure P1 offsets.
|
Bui OPS
|
Stored beam & injection
|
|
Thursday, 5/25/06
|
|
|
0000-0300
|
Measure P1 offsets (continued).
|
Bui OPS
|
Stored beam & injection
|
0300-0500
|
SR training.
|
S Flood
|
Stored beam & injection
|
0500-0700
|
Collect rtfb data.
|
Sun
|
Stored beam & injection
|
0700-0900
|
Investigate P1/P0 rms.
|
Lenkszus Singh Sun
|
Stored beam & injection
|
0900-1100
|
PEM testing.
|
OPS
|
Stored Beam & Injection
|
1100-1500
|
Test S19 hard x-ray bpm. Shutter support required.
|
Singh Hahne Rosenbaum
|
Stored Beam & Injection
|
1500-1700
|
Install P1 offsets.
|
Bui
|
Stored Beam & Injection
|
1700-2100
|
Validate bplds.
|
Bui
|
Stored Beam & Injection
|
2100-2300
|
Booster training.
|
Poncin
|
Limited Injection
|
2300-2400
|
SR training.
|
S. Flood
|
Stored Beam & Injection
|
|
Friday, 5/26/06
|
|
|
0000-0100
|
SR training.
|
S. Flood
|
Limited Injection
|
0100-0400
|
Intra girder beam based measurements.
|
Emery
|
Stored Beam & Injection
|
0400-0800
|
ID xbpm tests.
|
Hahne
|
Stored Beam & Injection
|
0800-1600
|
PSS validations
|
SI group
|
No beam
|
0800-1600
|
Various 420 RF system studies/tests
|
RF Group
|
No beam
|
0800-0830
|
Prepare for Zone F Access
|
OPS/PFS
|
No beam
|
0830-0930
|
installing a different CPU board in iocinjtime
|
Lenkszus
|
No beam
|
0830-0930
|
Repair/replace RF cavity IR detector
|
Morrison
|
Zone F access
|
0900-1030
|
Document the configuration for the new septum regulators if Booster & SR (Septums off)
|
Hillman/Puttkammer
|
No injection
|
1600-1800
|
Booster training.
|
Poncin
|
Limited Injection
|
1800-2200
|
PAR fundamental phase modulation.
|
Yao Grelick
|
Stored Beam & Injection
|
2200-2400
|
Characterize new sextupoles.
|
Sajaev
|
Stored Beam & Injection
|
|
Saturday, 5/27/06
|
|
|
0000-0200
|
Characterize new sextupoles (continued).
|
Sajaev
|
Stored Beam & Injection
|
0200-0800
|
Optimize vertical kick for high intensity.
|
Harkay
|
Stored Beam & Injection
|
0800-1000
|
Collect FF data.
|
Singh
|
Stored Beam & Injection
|
1000-1400
|
Investigate P1/P0 rms.
|
Singh Sun
|
Stored Beam & Injection
|
1400-1600
|
Collect hybrid fill intensity.
|
Sun
|
Stored Beam & Injection
|
1600-2200
|
Orbit recovery.
|
Singh
|
Stored Beam & Injection
|
1700-1900
|
Booster training.
|
Poncin
|
Limited Injection
|
2200-2400
|
OPEN
|
|
|
|
Sunday, 5/28/06
|
|
|
0000-0400
|
OPEN
|
|
|
0400-0600
|
Optimize vertical kick for high intensity.
|
Harkay
|
Stored Beam & Injection
|
0600-1000
|
set up pinhole camera and bunch purity monitor for the user run
|
Yang
|
Stored Beam & Occ. Inj.
|
1000-1400
|
Routine tests of SR PEM steering software
|
Emery
|
Stored Beam & Injection
|
1400-1800
|
Characterize each undulator effect on coupling and lifetime.
|
Emery
|
Stored Beam & Injection
|
1800-2000
|
Check encoders
|
Merritt
|
No Beam
|
1800-2000
|
Booster training.
|
Poncin
|
Limited Injection
|
2000-2400
|
Multibunch bursting instability investigation.
|
Harkay
|
Stored Beam & Injection
|
|
Monday, 5/29/06
|
|
|
0000-0200
|
Multibunch bursting instability investigation (continued).
|
Harkay
|
Stored Beam & Injection
|
0200-0700
|
OPEN
|
|
|
0700-1100
|
Operational orbit controllaw test with topup
|
Singh
|
Stored beam & injection
|
1100-1500
|
Check out CPU compensation.
|
Emery
|
Stored Beam & Injection
|
1500-1900
|
BPM prototype software tests.
|
Emery Pietryla
|
Stored Beam & Injection
|
1900-2100
|
Setup PAR and bunch cleaning system.
|
Yao
|
Stored Beam & Injection
|
2100-2400
|
Checking encoders
|
Merritt
|
No beam
|
|
Tuesday, 5/30/06
|
|
|
0000-0100
|
Checking encoders
|
Merritt
|
No beam
|
0100-0500
|
HOM measurements.
|
Harkay
|
Stored Beam & Injection
|
0500-0630
|
OPEN
|
|
|
0630-0800
|
Ready for TopUp 0+24*1
|
OPS
|
Store Beam & Injection
|