Machine Studies

Schedule for Run02-11, 2006

August 8th 0800 - August 9th 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 8/8/06

 

 

0800-0810

Collect BPM orbit data

OPS

Stored Beam & Injection

0810-0900

23BM end to end test

Nguyen

No Beam

0810-1100

Investigate PAR fundamental cavity turn-on problems

Grelick

No Injection 0810-1000

0810-1130

RF4 troubleshooting

RF Group

No beam

0900-1200

PEM testing

Soliday, Schroeder, Flood

Limited Injection

0900-1000

1200-1400

SR training.

S. Flood

Stored Beam & Injection

1400-1600

24BM shielding verification.

Ramanathan

Stored Beam & Injection

1400-1500

Software testing. Parallel to 24BM shielding verification.

Emery

Stored Beam & Injection

1600-1700

Dispersion correction test.

Emery Sajaev

Stored Beam & Injection

1500-1700

Booster training. Parallel to dispersion correction test.

Poncin

Limited injection

1700-1900

Test single bunch feedback aquisition.

Yao Gold

Stored Beam & Injection

1900-2300

ID and BM steering.

Erwin

Stored Beam & Injection

2300-2400

Single bunch vs rf voltage study.

Harkay

Stored Beam & Injection

 

Wednesday, 8/9/06

 

 

0000-0200

Single bunch vs rf voltage study (continued).

Harkay

Stored Beam & Injection

0200-0700

ID19 xray bpm study. Floor coordinator support required. No injection from 0300 to 0500.

Decker

Stored Beam & Injection

0300-0500

2 hrs PAR requalification

Oakley

No Injection

0700-0800

Prepare for user Beam

OPS

Stored Beam & Injection