Machine Studies

Draft Schedule for Run02-12, 2006

August 15th 0800 - August 16th 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 8/15/06

 

 

0800-0810

Collect BPM orbit data

OPS

Stored Beam & Injection

0810-0900

23BM end to end test

Nguyen

No Beam

0900-1100

SR training.

S. Flood

Stored Beam & Injection

1100-1500

21ID shielding verification.

Salazar

Stored Beam & Injection

1500-1800

Orbit setup for 1296 bunches operation.

Singh

Stored Beam & Injection

1800-2000

Investigate xbpm noise.

Hahne

Stored Beam & Injection

2000-2200

Further tests of corrector feedforward

Emery

Stored Beam & Injection

2200-2400

Cross-plane response measurement using RTFB.

Emery Xiao

Stored Beam & Injection

 

Wednesday, 8/16/06

 

 

0000-0300

Bunch length measurement vs current and RF voltage.

Sajaev

Stored Beam & Injection

0300-0500

PAR requalification.

Gagliano

No Injection

0500-0630

Booster training.

Poncin

Limited Injection

0300-0630

Xbpm studies. Parallel to training.

Decker

Stored beam

0630-0800

Prepare for user Beam

OPS

Stored Beam & Injection