Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Tuesday, 6/13/06
|
|
|
0800-0810
|
Collect xbpm orbit data
|
Ops
|
Stored Beam & Injection
|
0800-1500
|
2 hrs Booster training
|
Poncin
|
Limited Injection
|
0810-1000
|
PSS end to End tests
|
Friedman
|
No Beam
|
0810-1000
|
Inspect Booster PS current feedback loops
|
Puttkammer
|
No Injection
|
0810-0930
|
RF1 PLC interlock work
|
Horan
|
No Beam
|
0810-1100
|
Modulator and klystron noise measurements
|
Pasky/ Cours
|
No Beam 0800-1000
Limited Injection 1000-1100
|
0830-0930
|
Set xbpm limits for 30ID
|
Hahne
|
Access Zone E
|
0830-0930
|
Document ACIS gate switches.
|
Hillman Hogrefe
|
Access Zone E
|
0900-1000
|
Repair replace Johnson Controls NCM module.
|
Kailus
|
No Beam
|
0900-1000
|
Manually xlose isolation valve for P-SR-40.
|
Swetin
|
No beam
|
1100-1200
|
Canted undulator steering training.
|
OPS
|
Stored beam & injection
|
1200-1600
|
324 bunches instability study.
|
Harkay
|
Stored beam & injection
|
1200-1400
|
Booster training. Parallel to 324 bunches instability study.
|
OPS
|
Limited injection
|
1600-2000
|
Xbpm software testing.
|
Decker
|
Stored beam & injection
|
2000-2200
|
Investigate booster erratic efficiency change.
|
Sereno
|
Stored beam & injection
|
2200-2400
|
Continue new S2 study.
|
Sajaev
|
Stored beam & injection
|
|
Wednesday, 6/14/06
|
|
|
0000-0200
|
Continue new S2 study (continued).
|
Sajaev
|
Stored beam & injection
|
0200-0700
|
Implement booster longitudinal controllaw.
|
Sereno
|
Stored beam & injection
|
0700-0800
|
Prepare for user beam
|
Ops
|
Stored Beam & Injection
|