Machine Studies

Draft Schedule for Run02-3, 2006

June 13th 0800 - June 14th 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 6/13/06

 

 

0800-0810

Collect xbpm orbit data

Ops

Stored Beam & Injection

0800-1500

2 hrs Booster training

Poncin

Limited Injection

0810-1000

PSS end to End tests

Friedman

No Beam

0810-1000

Inspect Booster PS current feedback loops

Puttkammer

No Injection

0810-0930

RF1 PLC interlock work

Horan

No Beam

0810-1100

Modulator and klystron noise measurements

Pasky/ Cours

No Beam 0800-1000

Limited Injection 1000-1100

0830-0930

Set xbpm limits for 30ID

Hahne

Access Zone E

0830-0930

Document ACIS gate switches.

Hillman Hogrefe

Access Zone E

0900-1000

Repair replace Johnson Controls NCM module.

Kailus

No Beam

0900-1000

Manually xlose isolation valve for P-SR-40.

Swetin

No beam

1100-1200

Canted undulator steering training.

OPS

Stored beam & injection

1200-1600

324 bunches instability study.

Harkay

Stored beam & injection

1200-1400

Booster training. Parallel to 324 bunches instability study.

OPS

Limited injection

1600-2000

Xbpm software testing.

Decker

Stored beam & injection

2000-2200

Investigate booster erratic efficiency change.

Sereno

Stored beam & injection

2200-2400

Continue new S2 study.

Sajaev

Stored beam & injection

 

Wednesday, 6/14/06

 

 

0000-0200

Continue new S2 study (continued).

Sajaev

Stored beam & injection

0200-0700

Implement booster longitudinal controllaw.

Sereno

Stored beam & injection

0700-0800

Prepare for user beam

Ops

Stored Beam & Injection