Schedule for Run03-6, 2006

November 7th 0800 - November 8th 0800

 

Time

Descriptions

Studiers

SRStatus

 

Tuesday, 11/7/06

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

re-install phase shifter card in Booster/Injection LLRF VXI crate

Horan

No Injection

0830-0900

Record corrector serial numbers

Jaski

Access Booster

0830-0930

Investigate 21ID safety shutter

Vacuum grp/Banks

Access Zone C

0830-1000

Replace IR thermometer on Booster cav #3

Morrison

Access Booster

0900-1100

SR Operator requalification (no beam the first hour)

OPS/Schroeder

no beam/Stored beam & inj.

1100-1200

SR Operator training

Poncin

Stored beam & Injection

1200-1400

test S8B:P0 bpm

Sun/Singh

Stored beam

1400-1600

Test P0 feedback drive circuits (24 singlets)

Yao

Stored beam

1600-2000

id xbpm alignment work (324 singlets)

Decker/Schroeder

Stored beam

2000-2100

Operator requalification

OPS/Schroeder

Stored beam & Injection

2100-2400

Scanning vertical emittance for pinhole characterization

Sajaev/Emery/Yang

Stored beam

 

Wednesday, 11/8/06

 

 

2400-0100

Scanning vertical emittance for pinhole characterization

Sajaev/Emery/Yang

Stored beam & Inj.

0100-0300

Increase 324 bunch lifetime

Sajaev/Emery

Stored beam & inj

0300-0700

CPU compensation

Emery

Stored beam

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection