Machine Studies
Draft Schedule for Run01-2, 2007
February 6th 0800 - February 7th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 2/6/07 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-1000 |
Install new ion pump controller @ RF3 |
RF group |
RF group |
0810-1000 |
Troubleshoot P3BMT1 |
Puttkammer |
No Injection |
0810-1000 |
Repair bad analog readbacks. |
Puttkammer |
No beam |
0810-1000 |
Converter swapouts |
Fors |
No Beam |
0810-1100 |
Replace L1 water pump motor |
Ferry |
No Injection |
0830-0930 |
Repair 12ID gap limit switch. |
Grimmer |
Access Zone B |
0830-0930 |
Reset xbpm limits on 17IDP2Y |
Hahne |
Access Zone C |
0830-0930 |
Replace termination on DCCT test line |
Pietryla |
Access Zone F |
1000-1030 |
PAR PEM testing |
Yao |
Limited injection |
1030-1100 |
Restore SR beam. |
OPS |
Stored beam & injection |
1100-1500 |
Linac beam study. |
Pasky |
Limited injection |
1100-1500 |
S32 shielding verification. |
Ramanathan |
Stored beam & injection |
1500-1600 |
Punch down S17 correctors. |
Emery |
Stored beam & injection |
1500-1600 |
Test spare bunch current monitor. Parallel to punch down S17 correcotrs. |
Varotto |
Stored beam |
1500-1900 |
Test linac controllaw. Parallel to everything. |
Sereno |
Injection possible always |
1600-1800 |
Measure SR DCCT frequency spectrum with various fill patterns. |
Pietryla |
Stored beam & injection |
1800-2000 |
Test single bunch feedback. |
Yao |
Stored beam & injection |
2000-2200 |
Restore PAR orbit bump and optimize beam. |
Yao |
Limited injection |
2000-2400 |
Xbpm alignment. First 2 hours parallel to PAR work. |
Decker & lottery winner |
Stored beam & injection |
|
Wednesday, 2/7/07 |
|
|
0000-0200 |
Xbpm alignment (continued). |
Decker & lottery winner |
Stored beam & injection |
0200-0700 |
Test all ID 10-m beta X lattice |
Sajaev |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |