Machine Studies
Schedule for Run02-10, 2007
July 31st 0800 - August 1st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 7/31/07 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0830 |
Reboot interleaving PS DSP's |
Fors |
No Injection |
0810-1000 |
Measure S32 PS cabinet temp & air flows |
Puttkammer |
No Beam |
0810-0930 |
Replace fan in one of the SR Tune Measurement amplifiers |
Brill |
No impact |
0810-0930 |
Replace blower S38 RF Cav 1 |
Pace/McKenzie |
Access Zone F |
0810-0900 |
Swap out S3A:V4 P.S. |
P.S. Group |
No beam |
0810-1000 |
Conduct high voltage test of RF1 SCR cabinet circuitry |
RF Group |
No impact |
0830-0930 |
Troubleshoot S12 Cerenkov detector |
Gold & Yao |
Access Zone B |
0930-1000 |
Recover from access |
OPS |
Stored Beam & Inj. |
1000-1200 |
Troubleshoot S12 Cerenkove detector and beam loss detector study |
Yao/Dooling |
Stored Beam & Inj. |
1200-1400 |
Booster tune system test (parasitic) |
Yao |
Injection available |
1200-2000 |
Set-up S32 RHB lattice |
Sajaev/Emery |
Stored Beam & Inj. |
2000-2400 |
Orbit recovery – RHB lattice |
Singh |
Stored Beam & Top-Up |
|
Wednesday, 8/1/07 |
|
|
0000-0100 |
Test modifications to Linac Controllaws |
Pasky/Sereno |
Injection available |
0100-0630 |
LCLS – BPM studies |
Pasky/Sereno/ Erwin |
No injection |
0630-0800 |
Prepare for User beam 0+24*1 RHB Top-Up |
OPS |
Stored Beam & Injection |