Machine Studies
Schedule for Run02-11, 2007
August 7th 0800 - August 8th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 8/7/07 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0830 |
Reboot iocbdg1 |
Stevens |
No Injection |
0810-0930 |
Install VME Bus analyzer in iocbbpm2 |
Lenkszus |
No Injection |
0810-1000 |
Condition Booster RF Cavities with higher gap voltage |
Horan |
No injection |
0810-1000 |
Replace failed starter in Bldg. 450 MCC (degassifier off-line – Process water temp & pressure |
Kailus |
No beam |
0810-1000 |
Check/Repair L2 RF Modulator pre-pulser |
Grelick |
No injection |
0810-1000 |
Test FPGA-based 352MHz phase detector |
Horan |
No Beam |
0810-1000 |
Test recent CPU failures |
Deriy |
No Beam |
0930-1000 |
Reinstall FSIC03 in iocsbpmdp |
Lenkszus |
No Beam |
1000-1200 |
Evaluate MXA spectrum analyzer for SR tune measurement |
Yao/Gold |
Stored beam & Occ. inj. |
1200-1400 |
Test SR loss monitor data acquisition experiment designer setup |
Yao |
Stored beam & inj. |
1400-1600 |
Adjust booster (and BTS) energy for loss-less injection into the ID32 RHB lattice – May need extra rf voltage for booster |
Emery/Xiao/ Others |
Stored beam & inj. |
1600-1800 |
Calibrate kicker strength with BPM histories |
Sajaev/Emery |
Stored beam & inj. |
1800-2100 |
Check the functioning of the SR beta function measurement using quad scans |
Emery |
Stored beam & inj. |
2100-2400 |
LCLS BPM studies |
Pasky/Erwin/ Sereno/Lill |
No injection |
|
Wednesday, 8/8/07 |
|
|
0000-0200 |
LCLS BPM studies |
Pasky/Erwin/ Sereno/Lill |
No injection |
0200-0700 |
19ID studies, low current, PS2 shutter open |
Decker/Rosenbaum |
Stored Beam & injection |
0700-0800 |
Prepare for User beam (0+24*1 RHB – Top-up) |
OPS |
Stored Beam & Injection |