Machine Studies

Schedule for Run02-2, 2007

June 5th 0800 - June 6th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, 6/5/07



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0830

Reboot ctlapps3l

Smith/Sheehan

Limited Injection

0810-0830

Reboot interleaving DSPs

Puttkammer

No Injection

0810-0900

Inspect SR dipole capacitor bank

Fors

No Beam

0810-0900

23ID PSS end to end test

Hawkins

No Beam

0810-0900

24ID PSS end to end test

Budz

No Beam

0810-0900

26ID PSS end to end test

Boron

No Beam

0810-0930

Replace L5 water seal

Ferry

No Injection

0810-1000

CMPSI fiber output testing

Pietryla

No Beam

0810-1000

Re-install TCU at RF2 troubleshoot RF4 TCU

Horan

No Beam

0830-1230

Test PC gun switchover PEM

Sereno/Soliday

Limited Injection

1030-1330

RMS calculation test

Singh/Lenksus

Store Beam

1230-1630

Test cathode laser cleaning script

Sereno/Shang

No impact

1330-1530

RTFB Orbit Tests

Singh

Stored Beam

1530-1630

Swap pre-amps

Hahne

Stored Beam

1630-1800

XBPM calibration

Hahne

Stored Beam

1800-2400

Xbpm alignment work

Decker/Hahne

Stored Beam & Inj.


Wednesday, 6/6/07



0000-0200

Transverse Coherent Damping Rate Measurement

Emery

Stored beam & Inj.

0200-0400

Fiber optic radiation loss monitor characterization

Emery/Dooling

Stored beam & Inj.

0400-0700

Tune scans & harmonic sextupole knobs

Emery

Stored beam & Inj.

0700-0800

Prepare for User beam (24 singlets, Top-Up)

OPS

Stored Beam & Injection