Machine Studies

Schedule for Run02-4, 2007

June 18th 0800 - June 20th 0800



Time

Descriptions

Studiers

SR Status


Monday, 6/18/07



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-1600

LCLS studies

Lill, Pasky, Sereno, Erwin

No Injection

0810-1000

Investigate S40 Cav2 Tuner RF Fingers DS Thermocouple readbacks

RF Group

No impact

0900-1200

Investigate S6A:P1, S7B:P1 (parasitic)

Sun, Singh

Stored Beam

1300-1500

Replace/repair S37 RF Cavities Blower

Morrison

Access Zone F

1300-1400

Investigate S40 Cav2 Tuner RF Fingers DS Thermocouple in tunnel

RF Group

Access Zone F

1600-2000

Set-up hybrid

Emery, Sajaev

Stored beam & Inj.

2000-2400

Test deflecting cavity lattice

Emery, Sajaev

Stored beam & Inj.


Tuesday, 6/19/07



0000-0300

Coherent damping studies

Emery, Harkay

Stored beam & inj.

0300-0500

Test S35 pinger module (single bunch)

Harkay, Lenkszus

Stored beam & inj.

0500-0700

RMS calculation test

Singh, Lenkszus, Shang

Stored beam & inj.

0700-0900

Investigate S6A:P1, S7B:P1 (parasitic)

Sun, Singh

Stored beam

0700-1100

LCLS studies

Lill, Pasky, Sereno, Erwin

No Injection

0900-1100

Operational test of process water pump switchover, high pressure safety switch and frequency drive (S3&4 P.S. off)

Ferry

No beam

0900-1100

Investigate S:IK1 setpoint problems

Fors

No Beam

0900-1000

Switch from RF-3 to RF-2

Horan

No Beam

0900-1100

Troubleshoot B3C1V

Deriy

No Injection

0900-1100

CMPSI fiber output testing

Pietryla

No Beam

1100-1200

Reboot ioclid6

Varotto

Limited injection

1000-1100

Replace S6A:P1 Bergoz module

Sun

No Beam

1000-1100

Reboot ctlapps3l

Smith,Sheehan

Stored beam & Injection

1000-1100

Test flag/MPS script

Stevens

No Beam

1100-1200

BPLD validations (5-ID, 7-ID)

Bui

Stored beam & inj.

1200-1300

Investigate L2 phase changes

Grelick

Occ. Inj.

1200-1300

Shielding verification 14-ID-B (50 mA)

Chaffee

Stored beam

1200-1300

Shielding verification 11-ID (will need steering)

Chaffee

Stored beam

1300-1600

BPM database for hybrid fill (Top-up)

Singh

Stored beam & Top-up

1600-2000

Tune scan

Sajaev, Emery

Stored beam & inj.

2000-2400

Current scan for RHB lattice

Sajaev

Stored beam & inj.


Wednesday, 6/20/07



0000-0630

OPEN



0630-0800

Prepare for User beam

OPS

Stored Beam & Injection